Agreed that the financial position for the second quarter, be noted.
Customer and Corporate Services Select Committee 2005/2006 agreed this item on Thursday 11 November 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the financial position for the second quarter, be noted.
1. That Members be aware that the overall financial position is consistent with the approved budget and that no overall corrective actions are required to be approved by the City Council. 2. Relevant background information
1. The Central Services portfolio budget for 2004/05 is £4.6 million (net of recharges to portfolios and including relevant costs of LDL Joint Venture - Appendix A). There is in addition £6.3 million of planned capital expenditure (Appendix B). This report anticipates that overall spending for services within this portfolio will be maintained within allocated budgetary resources.
2. Additional spend on various initiatives is now committed or planned to take place during the year for which funding resources were identified last financial year and brought forward as Reserves. The relevant budgets have now been adjusted to reflect this.
3. In forecasting the above financial position, a request to draw down funding of £5,500 from earmarked reserves has been taken into account. This is in respect of lease costs for premises at Old Hall Street.
3. Key issues
1. This Financial Review is based on the best information available as at the end of August, but updated where appropriate for more recent information.
2. This report forecasts that overall spending for services within the portfolio will be contained within allocated budgetary provision.
3. There are several areas within Central Services Portfolio where there is potential for planned expansion of corporate initiatives.
This forecast assumes that any spend above current provision resulting from such expansion is either financed via earmarked reserves or recharged on a basis agreed with Service Managers at no additional net cost to the Council overall.
4. The effects of structural changes within the Council have been taken into account as far as possible when forming a view on the budgetary position.
5. Mindful of the need to provide the right high quality services while operating within current budgetary provision, the Executive Director is in the process of scrutinising all budgets within the management portfolio, challenging current spend and examining methods of generating additional income. This exercise is ongoing and part of a longer-term initiative.
6. In the short term, the Executive Director is confident that overall spending within the management portfolio can be managed within allocated budgetary resources. 4. Conclusions
1. This report reviews the financial position for Central Services for 2004/05 and concludes that the overall spend for revenue and capital can be contained within available budget allocations.
5. Key to any abbreviations used
1. None.
6. Documents attached
Appendix A – Central Services Revenue Monitor – Second Quarter 2004/05
Appendix B – Central Services Capital Monitor – Second Quarter 2004/05
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Central Services Portfolio Financial Review Quarter 2 2004/05Report | 4 pages | DownloadRead as text |
PDF |
Q2 Monthly financial statementsAppAReport | 1 pages | Download |
PDF |
Q2 Monthly financial statementsAppBReport | 1 pages | Download |
Follow Customer and Corporate Services Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2006 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 2 March 2006 be approved as a true record. | Agreed | Open |
| 20 Apr 2006 | Customer and Corporate Services Select Committee Annual ReportAgreed that the Committee’s Annual Report for 2005/06 be approved. | Agreed | Open |
| 20 Apr 2006 | Internet/Intranet/Extranet DevelopmentsAgreed that the report be noted. | Agreed | Open |
| 20 Apr 2006 | Learning and Development Service Progress ReportAgreed that the report be noted. | Agreed | Open |
| 20 Apr 2006 | Diversity and Social Inclusion Update for 2005/06Agreed that the report be noted and the recommendations set out in relation to the 2006/07 programmes, be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.