Resolved that – (i) in line with the Sure Start Unit approval to proceed, the Education Capital Programme be amended to include the following proposed capital projects: · Wavertree Children Centre (Mystery Day Nursery site) - Indicative Budget £450,000; · Walton Children centre (SCOPE Day Nursery site) - Indicative Budget £750,000; · Corinthian Children Centre (Corinthian Infant School site) - Indicative Budget £2,400,000; and · Garston Children centre (Hilda Mason Day Nursery site) - Indicative Budget £20,000; and (ii) reports be submitted for approval of tenders in line with City Council Financial Regulations and Standing Orders.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This report seeks permission to amend the Education Capital Programme to include the following Children Centre capital projects to be developed by March 2006:
• Wavertree Children Centre (Mystery Day Nursery site) • Walton Children Centre (SCOPE Day Nursery site) • Corinthian Children Centre (Corinthian Infant School site) • Garston Children centre (Hilda Mason Day Nursery site)
The Children Centre First Phase Strategic Plan (Report DE.122.03) approved 16 Children Centres to be developed as part of the First Phase (including those identified above) funded by General Sure Start Capital Grant of £7,124,639. The Sure Start Unit capital process requires approval of capital projects at a number of stages triggering the release of a percentage of capital funding. The Sure Start Unit has approved the Implementation Plans of the proposed Children Centres named above giving permission to proceed on the related capital projects. Capital funding can therefore be claimed at this stage towards professional fees up to a maximum of 5% of the overall capital building costs.
Executive Director recommendation: Colin Hilton recommends that –
1. In line with the Sure Start Unit approval to proceed, the Education Capital Programme be amended to include the following proposed capital projects:
• Wavertree Children Centre (Mystery Day Nursery site) - Indicative Budget £450,000 • Walton Children centre (SCOPE Day Nursery site) - Indicative Budget £750,000 • Corinthian Children Centre (Corinthian Infant School site) - Indicative Budget £2,400,000 • Garston Children centre (Hilda Mason Day Nursery site) - Indicative Budget £20,000
2. Reports be submitted for approval of tenders in line with City Council Financial Regulations and Standing Orders. Key Decision: Yes
Forward Plan: No – appropriate Notice will be served under the Constitution
Implementation effective from: 3 December 2004
Time-scale for action: Sure Start Unit requires capital programmes to be completed by March 2006.
Reason(s) for Recommendation: The Sure Start Unit capital process enables the draw down of capital funding in a staged process following approval of the Children centre Implementation Plan. The 4 centres named in this report have received approval to proceed. The capital projects identified in this report are all being developed by 20/20.
Alternative options considered: The issuing of capital codes may be delayed until the tender process is completed. However, the management of payments from within one revenue code for 4 capital programmes is difficult to monitor, particularly as the programmes vary greatly in size and complexity. It is recommended that individual budget codes be established as soon as possible to facilitate accurate tracking of individual programme spend and payment of 20/20 invoices.
Consultation: • Education Finance – Capital Programme Officer • 20/20 • School Planning and Regeneration • Sure Start Unit
Financial implications: Report DE.122.03 accepted the General Sure Start Capital Grant of £7,124,639. The capital grant must be spent by March 2006 to meet Sure Start Unit requirements. A financial profile for each Children Centre capital programme will be submitted with tender details to the Sure Start Unit and a final decision regarding approval of budget/costs will be made by the Sure Start Unit at this point. 20/20 have advised that proposals/estimates to date are within the capital programme allocation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.