Resolved that – (i) the City Councils Capital Programme be adjusted to reflect the revised expenditure on this project for a sum up to £1,889,991 phased over financial years 2004/05 to 2006/07 as set out in the report submitted; (ii) subject to the approval of the Big Lottery Fund the City Council accepts · the revised tender offer of £1,544,499 from Walter Carefoot & Sons Limited for the construction of the St.Margaret’s CE High School Sports Hall and Indoor Centre; and · the expected offer of a further £243,036 funding from the Big Lottery Fund towards meeting the increased project costs; and (iii) Officers be authorised to act immediately upon the receipt of this approval .
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
MOSSLEY HILL WARD STATUS – PUBLIC LL/29 Portfolios: Education and Lifelong Executive Members: Learning / Leisure, Sport and Culture / Councillor Paul Clein Resources Councillor Warren Bradley Councillor Keith Turner
Date of submission: Subject: Big Lottery Fund (BLF) PE 3 / 6 / 8 December 2004 and Sport –St. Margaret’s CE High School New Sports Hall and Cricket Centre of Excellence Report No./Background papers: Contact Officer: DE/071/04 Stephen Tiffany Ext 233 8135 Mike Kearney Ext 233 6329
Executive summary: The purpose of this report is to:
(i) advise the Executive Board on the outcome of the Stage 2 NOF (now known as the ‘Big Lottery Fund’ - BLF) PE and Sport application in respect of St. Margaret’s CE High School for the development of a new sports hall and cricket centre of excellence located within the existing school site;
(ii) obtain authority subject to the approval of BLF to accept the revised lowest tender of Walter Carefoot & Sons Limited in the sum of £1,544,499.00 for the Construction of a new sports hall and indoor cricket centre for St. Margaret’s CE High School as part of the City Council’s New Opportunities Fund (now Big Lottery Fund) PE and Sport Portfolio;
(iii) obtain authority to accept additional BLF grant funding in the sum of £243,036 which has been re-allocated to this scheme as a result of recent revisions to the current City Council BLF PE and Sport Portfolio.
A separate report identifying these changes to the Portfolio will be submitted to the Executive Board.
Background Members are aware that at its meeting on 21 March 2003 the Executive Board approved report DE/025/03 which outlined the principles of the BLF for PE and Sports Initiative in relation to the allocation of £9.2m made to the City Council.
The following report elaborates on these principles and indicates the current position in relation to the delivery of the Priority 5 Project (St. Margaret’s CE High School) which is contained within the City Council’s BLF PE and Sport Portfolio.
As stated in the previous report the estimated total project costs for the development at St. Margaret’s CE High School was £1.4m. Since then, further development of the scheme has been required in order to comply with Sport England and Governing Body design guidance. The result of these additional requirements together with current building inflation costs has increased the total project costs to £1.645m. The City Council’s BLF PE and Sport Portfolio has therefore been amended accordingly in order to reflect the increased costs. These amendments have been reported (Report No. DE/025/04) previously to the Executive Board by the BLF PE and Sport Portfolio Manager.
Officers submitted the stage 2 application to BLF in October 2003 containing details of the new facilities being developed which include: • 4 badminton court sports hall • fitness suite • ancillary accommodation • External works
Subsequently, at a meeting held on 24 February 2004 the Big Lottery Fund approved the Stage 2 application.
Capital Funding February 2004 BLF Grant: £567,955 School Contribution £154,746 DFC Allocation: £213,254 LCVAP contribution: £711,000 ----------------- Total Project Cost £1,646,955
Construction Tenders: Tenders for a ‘Traditional’ contract were issued in August 2004 to six construction firms in accordance with City Council Standing Orders. The pre- tender estimate was circa £1.45m and the lowest tender submitted was by Walter Carefoot & Sons Limited in the sum of £1,599,074. Following receipt of the tenders the contractor has identified savings within his tender totaling £44,575 resulting in a revised tender offer of £1,544,499 however; their revised tender together with other associated costs (professional fees etc) cannot be contained within the total project cost without additional funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.