Resolved
Agreed that the report be noted.
Liverpool City Council
Report to: Customer and Corporate Select Committee
Subject: Risk Management Register
Date: 10 February 2005
Reporting officer: David McElhinney
Contact officer: Gareth Davies – Ext : 0151 225 3752
Ward: N/A – Corporate Issue
1. Purpose and recommendations
This is the first in a series of reports providing members with the progress being made in managing any risk within Liverpool Direct Ltd. A previous report provided details of a broad view of the risks that exist across the four portfolios of ICT, HR&P, LD Connect and Revs and Bens.
2. Relevant background information
The management of risk is not a new activity across LDL, indeed risks have been identified and monitored ever since the Joint Venture with BT began in July 2001. Several schemes are in place to manage risks appropriately - based on a product known as the AIR database which essentially provides for regular review of action plans and escalation as necessary. With the adoption of the City Council wide ALARM scheme to monitor and control risk on a common platform, a reassessment of the key risks within LDL has been undertaken. This has meant more stringent checks and assessments being made on the type of risk, their likelihood and the potential impact that would occur should the risk materialise and additionally the progress of mitigation plans to prevent or reduce their severity.
As a result the list is now much reduced in number so that the risks within the register are only those considered to have a major and cross-Council consequence were they to occur.
In a separate initiative, contact and advice has been sought from Steve Wilkins of the Resources Portfolio regarding training and the prospect of a Risk Assessment Workshop is currently under consideration. The aim would be to provide awareness of risk management in all its forms and, therefore, create greater consciousness amongst a much wider audience than at present. This in turn, we believe, would enable a network of risk registers from the minor to the significant to be established, all contributing to reducing the possibility of an unforeseen incident.
3. Key issues
o To consolidate all existing Risk Management systems into a single unified reporting scheme o Relevant training for members of staff involved in the management of risks o Engagement of all LDL people in recognising that risks need to be identified and managed proactively
4. Conclusions
The LDL Senior Management Team is confident that the risks identified and included in the risk assessment form attached are being carefully managed and regularly monitored. 5. Key to any abbreviations used
LDL – Liverpool Direct Ltd AIR – Assumptions, Issues and Risks Database (used in ICT) ALARM – National Forum for Risk Management in the Public Sector
6. Documents attached
Appendix 1 – LDL Risk Assessment Form
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LDL Risk Assessment Jan 05Appendix 1 | 1 pages | Download |
PDF |
Risk Management RegisterReport | 3 pages | DownloadRead as text |
Follow Customer and Corporate Services Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2006 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 2 March 2006 be approved as a true record. | Agreed | Open |
| 20 Apr 2006 | Customer and Corporate Services Select Committee Annual ReportAgreed that the Committee’s Annual Report for 2005/06 be approved. | Agreed | Open |
| 20 Apr 2006 | Internet/Intranet/Extranet DevelopmentsAgreed that the report be noted. | Agreed | Open |
| 20 Apr 2006 | Learning and Development Service Progress ReportAgreed that the report be noted. | Agreed | Open |
| 20 Apr 2006 | Diversity and Social Inclusion Update for 2005/06Agreed that the report be noted and the recommendations set out in relation to the 2006/07 programmes, be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.