Housing Revenue Account Financial Review December 2004 (3rd Quarter)

Agreed Committee 2 papers

Housing and Community Safety Select Committee 2005/2006 agreed this item on Tuesday 1 March 2005. Below is the council's own wording, with the papers it was decided on.

Item72

Resolved

Agreed that the forecast reduction of £1,195,000 in the overall Housing Revenue Account working balance be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Housing and Community Safety Select Committee 2005/2006, 5 pages

Recommendation

2. That Members note the forecast reduction of £1,195,000 in the overall HRA working balance.

1 2. Relevant background information

INFORMATION:

3. The HRA’s 2004/05 2nd Quarter Financial Review, (FMS/50/04) was considered by the Housing and Neighbourhoods Select Committee on 23 November and forecast a HRA Working Balance of £2.294 million.

4. As per Annexe A, the HRA’s 2004/05 3rd Quarter Financial Review forecasts a Working Balance of £1.099 million. This is a reduction in the Working Balance of £1.195 million on the position reported in the 2nd Quarter Financial Review.

5. The HRA’s 2004/05 3rd Quarter Financial Review is based on the financial information at the end of November 2004, but updated where appropriate for more recent data. The principal variances and updates on budgets at risk are highlighted below.

3. Key issues – Variances / Areas of Concern Repair & Maintenance

6. As per Annexe A an adverse variation of £1.348 million is forecast on the Repairs account. Table 1 provides an analysis of this variance:

Table 1: Repairs, (2004/05 3rd Quarter Financial Review)

Variance AED Service Area (£000’s) Note Repairs Contract 700 Enterprise - voluntary severance costs. Cath Green Repairs -19 Several minor favourable variances. Consultancy Sub-Total 681 Eric Disrepair Unit 667 Voluntary severance costs. Wilkinson Total Repairs 1,348 Adverse Variance

Repairs Contract

7. With the objective of delivering service improvements and increased value for money, Enterprise-Liverpool has restructured and reduced its workforce with the agreement of the City Council, under the agreement entered into by the City Council, firstly with Interserve and now with Enterprise-Liverpool. The costs associated with this restructure are forecast to be £700,000 and

2 are required to be financed by the City Council.

Disrepair Unit

8. The number of cases received by the Disrepair Unit has reduced significantly. It was thought that the Unit’s order book would be bolstered by work from the Eastern Fringe RSLs however the number of cases received has not been sufficient to prevent a £400,000 budget deficit on the account.

9. This deficit is forecast to continue and thus a voluntary severance/early retirement package was offered to staff within the Disrepair Unit. 26 staff accepted the severance/retirement offer resulting in costs of £667,000. These costs will be incurred in the current year and will be financed by via cost reductions on employee salaries over the next three years.

Repairs Litigation Case

10. The City Council is involved in litigation proceedings in relation to the termination of the repairs contract with Omnisure, (SGI) in 2002. An agreement has not been reached with Ominsure via mediation. Costs associated with this case are forecast to be significant.

11. Regeneration Finance is updating the financial forecast with respect to this case via regular contact with Legal Services, who are managing the case. Members will be provided with a report on the progress of the case via the next quarterly HRA Financial Review.

Depreciation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Revenue Account Financial Review December 2004 (3rd Quarter)Report 5 pages DownloadRead as text
PDF
Housing Revenue Account Financial Review December 2004 chart405Report 1 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Housing Revenue Account Financial Review December 2004 (3rd Quarter)This decision
  2. 2008/09 housing revenue account budgetAgreed
  3. 2008/09 Housing Revenue Account Budget (NH/19)Approved
  4. Housing Revenue Account 2007/08 Quarter 2 Financial MonitorAgreed
  5. Housing Revenue Account 2007/08 Quarter 1 Financial MonitorAgreed
  6. Housing Revenue Account Financial Monitor Quarter 3 2006/07Agreed

More from Liverpool Housing and Community Safety Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
3 Apr 2006 Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 7 February 2006 , be approved as a true ... Agreed Open
3 Apr 2006 Minutes of Scrutiny PanelsAgreed that;- the Minutes from the meeting of the Building Maintenance Scrutiny Panel held on 3 March 2006; be approv... Agreed Open
3 Apr 2006 Question TimeAgreed that the information requested be submitted to a future meeting of this Committee .. Agreed Open
3 Apr 2006 Gateacre Neighbourhood Committee - Lanfranc Close/Castletown CloseIt was agreed that: a) The Neighbourhood Committee are in full support of the residents and request that Officers and... Agreed Open
3 Apr 2006 Equalities Impact Assessment Statement, Community SafetyAgreed that;- § the information contained in the report be noted; and § the Community Safety team be thanked for thei... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies