Resolved
Agreed that the Environmental Scrutiny Panel be requested to look at what action can be taken to make sure that recycling boxes etc, left out for collection don’t become a hazard to disabled, blind or partially sighted people.
Regeneration & Environment Select Cttee 2005/2006 agreed this item on Thursday 3 March 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the Environmental Scrutiny Panel be requested to look at what action can be taken to make sure that recycling boxes etc, left out for collection don’t become a hazard to disabled, blind or partially sighted people.
Report to select committees
Liverpool City Council
Report to: Regeneration and Environment Select Committee
Subject: Six-month bring bank review
Report no: EDR/58/05
Date: 3rd March 2005
Reporting officer: Alan Smith (ext. 3683)
Contact officer: Alan Smith (ext. 3683)
Ward: All
1. Background information
Following the expansion of the number of recycling sites across the City from 26 to 170 a six-month review of the first tranche of banks has been undertaken. This note highlights the main findings.
The contract for placing bring banks out on site and emptying them is undertaken by Abitibi Consolidated Recycling Europe, (ACRE).
As part of the ACRE contract there is a requirement that, in order to hit its recycling targets, the City Council needs to increase the number of bring banks from the original 26 sites to ultimately 400.
Criteria were drawn up for the approval of new bring sites, and this was agreed by Regeneration & Environment Select Committee and the Executive Board (Appendix 1 details the criteria used). As part of the process all the locations are reviewed after 6-months. To date there have been 35 bring sites removed. The list of sites and the reason for their removal are shown in Appendix 2. The tonnage of material recycled at each site is shown in Appendix 3.
The vast majority of sites that are unsuitable are generally removed within 1 month of being placed out on location. There are however exceptions, as some sites have been subject to anti-social behaviour only after they have been set out for several months. Generally a site that is in place for over a month becomes a permanent site. Appendix 4 shows the incidence of anti- social behaviour at bring sites over time. The graph shows that after 3 months out on location the banks are subjected to very little vandalism.
Following the six month review of bring banks the next stage is to identify sites where banks for glass recycling can be located. A review is currently being undertaken to determine which existing sites can most easily accept glass banks. Once the sites have been identified then Ward Councillors will be consulted fully as to where the banks are located.
2. Key issues Bring banks are a very cost effective way of increasing recycling. 20% of the Liverpool City Council’s recycling is achieved through the use of bring banks. The use of bring banks and kerbside recycling complement each other, rather than preclude each other.
One consideration is the level of consultation with the public before new bring banks are placed out on site. Currently in Liverpool Ward Councillors are consulted on the placement of new bring banks. LCC compared how the London Borough of Barnet consults with householders in their district. Barnet consult with the public by producing a 4-page document which shows the locations plans for the proposed bring sites, (normally 2 to 3 sites per consultation exercise), along with reasons for why a particular Location is planned for a bring site, and allows for comments from the public. The document is then sent to the 1,000 households nearest to the proposed bank locations. The returns are then examined to see which site is the most popular and place the bring banks accordingly.
For Liverpool, such a process was costed at£100,000 per annum. This includes producing booklets, mailing costs and analysing the returns. It would also slow down the implementation of new sites, from the current practice of 2 weeks to at least 3 months. Therefore, the decision was taken to just consult with Ward Councillors.
3. Conclusions Bring Sites are a vital component in helping the Council increase the amount of material recycled. Bring sites complement the existing multimaterial collections service, not detract from it.
It is very hard to predict which locations will be subjected to anti-social behaviour before recycling banks are placed out on site.
4. Documents attached Appendix 1, shows the criteria currently used for siting bring banks
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
6 Month Bring Bank ReviewReport | 11 pages | DownloadRead as text |
Follow Regeneration & Environment Select Cttee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Mar 2006 | Neighbourhood Management Boundary Review - PresentationAgreed that – (a) the report and the views expressed by Members be noted and taken into consideration in the preparat... | Agreed | Open |
| 30 Mar 2006 | Liverpool Plus - Strategic Investment FundAgreed that (a) the report be noted; and (b) a further report be submitted to the Committee in due course | Agreed | Open |
| 30 Mar 2006 | Annual ReportAgreed that the annual report of the Select Committee for 2005/06 be noted. | Agreed | Open |
| 30 Mar 2006 | Carbon Dioxide EmissionsAgreed that (a) the report be noted; and (b) a further report be submitted in 6 months time to include - · the progre... | Agreed | Open |
| 30 Mar 2006 | Response to Council Motion - Pedistrian Crossing Muirhead AvenueAgreed that a report on the results of the traffic survey be submitted to the appropriate Neighbourhood Committee as ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.