Sustrans Grant for Surface and Access Improvements to the Liverpool Loop Line (REG/61)

Decided Executive 1 paper

Executive Board decided this item on Friday 4 March 2005. Below is the council's own wording, with the papers it was decided on.

Item145j

Resolved

Resolved that – (i) authority be granted to accept a funding allocation of £70,000 from Sustrans to fund a National Cycle Network & Links to School Programme in the financial year 2004/05; (ii) the Transportation Capital Programme Cycle Schemes budget be amended to reflect an increase of £70,000 in 2004/05 from £234,000 to £304,000; and (iii) expenditure be committed to the specific scheme as outlined in the report. Submitted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

This report outlines the offer of a £70,000 grant from Sustrans to undertake improvements to the surface and to access points along the Loop Line. The proposed improvements include resurfacing and improving the quality of the access points north of Belle Vale Road.

Executive Member / Director recommendation; Councillors Peter Millea, and Keith Turner / Charlie Parker:

That - (i) Authority be given to accept a funding allocation of £70,000 from Sustrans to fund a National Cycle Network & Links to School Programme in the financial year 2004/05; (ii) the Transportation Capital Programme Cycle Schemes budget is amended to reflect an increase of £70,000 in 2004/05 from £234,000 to £304,000; and (iii) expenditure be committed to the specific scheme as outlined in the report.

Key Decision: Yes

Forward Plan: No – appropriate notices will be published in accordance with the constitution

Implementation effective from: 11 February 2005

Timescale for action: The scheme is to be fully implemented by 1st April 2005. Reason(s) for Recommendation:

The acceptance of this funding allocation will allow significant improvements to the Loop Line to be made, which otherwise would not be possible.

Alternative options considered

Do nothing alternative.

Consultation

Internal departments including Regeneration Policy and Projects, Transport Policy Team and Regeneration Finance. External bodies including Sustrans, Merseyside TravelWise and 2o2o Liverpool Limited.

Financial implications

1.0Capital Implications

1.1As part of the National Cycle Network & Links to Schools Programme Sustrans have offered the City Council a grant of £70,000. In addition to this the City Council will contribute an additional £30,000 from the Cycling Schemes Programme of the Transport Capital Programme.

1.2The project will be managed from a financial perspective by the Regeneration Portfolio and therefore the capital budget of the Portfolio will require amending in 2004/05 to reflect the increased level of expenditure associated with this project.

2.0Revenue implications

2.1Negotiations are currently on going with Sustrans in relation to the Maintenance of the scheme. A report will be presented to Members in the New Year on the outcome of the discussions and wider issues which affect the Loop Line.

Best Value:

The Best Value process is inherent to the Travel to School Initiative and promotion of cycling. There are annual surveys carried out to track progress on School Travel Plan implementation and monitoring of the cycle route will be undertaken. Equality implications:

School Travel Plans help to support freedom of modal choice for all children. In addition the promotion of cycling provides individuals regardless of income a viable method of transport.

Corporate strategy:

The development of cycle routes to schools and cycle tracks strongly supports the implementation of the Local Transport Plan and Aim 5.3 of the Corporate Performance Plan.

Budget and Policy Framework:

The issues raised in the report are consistent with Liverpool City Council’s Budget and Policy Framework.

Community safety implications:

The scheme will deliver improvements to the Liverpool Loop Line in terms of access and surface quality which will improve safety.

Neighbourhood Implications:

Members have already identified issues relating to the Loop Line such as repair work needed in South Liverpool. The improvements to the surface and access points would be welcomed and support ongoing work.

Report attached:

Appendix A Appendix A

Loop Line Surface and Access Improvements

1.0Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sustrans Grant for Surface and Access Improvements to the Liverpool Loop Line (REG/61)Report 6 pages DownloadRead as text

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies