CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Resources Select Committee 2005/2006, Thursday 17 March 2005

Performance Indicators

Agreed Committee 1 paper

Resources Select Committee 2005/2006 agreed this item on Thursday 17 March 2005. Below is the council's own wording, with the papers it was decided on.

Item90

Resolved

Agreed that - a) in relation to BV8 (payment of invoices within 30 days), a report be submitted identifying the mechanism used to achieve this target and the effect the new procurement system will have on the process; and b) in relation to BV 78(a) and (b) (processing claims and changes) a graph be incorporated in the next update report indicating the progress being made by the service on a month by month basis.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Resources Select Committee 2005/2006, 4 pages

Performance Plan PI Report by Committee - January 2004/05

Resource Select - Chair : Councillor Andrew Makinson This report contains a listing of all statutory BVPIs, LPSAs and other local indicators published in the BVPP. The report shows performance up to the end of January 2004/05 for all PI's set to report monthly. Irrespective of the reporting frequency service managers for all PIs have been encouraged to use the comments field as they thought appropriate to comment on performance.

The report is grouped by Executive Director . The relevant AED responsible for the PI performance is shown, but where there is no relevant AED the Executive Director is named.

Explanation of Data columns and colour coding on database reports This report is black and white printer friendly and does not require a colour printer. Red, amber and green colours are used to grade PI performance figures displayed in this report. The key to the shading used to represent the colours is given at the bottom of each page of the report. A brief explanation of each of the data columns (numbered 1-11 on each page) used and their corresponding colour coding is given below.

Col Description Red Amber Green

(1) Ranking of indicator based on (Month) 04/05 Forecast Yearly outturn (Month) Forecast Yearly outturn (Month) Forecast Yearly outturn at measured against 2004/5 Met target (Month) 04/05 Forecast Yearly which is either = to or above Met top quartile of Met target 04/05 outturn at bottom quartile of Met Average (but not top quartile) or target 04/05 below Met target 04/05

(2) PI description no colour coding no colour coding no colour coding

(3) 2003/4 Liverpool City Council (LCC) outturn no colour coding no colour coding no colour coding

(4) % improvement in LCC outturn from 2002/3 to 2003/4 negative change no change positive change (calc: 03/04 outturn - 02/03 outturn / 02/03 outturn * 100)

(5) 2004/5 Metropolitan Top Quartile target no colour coding no colour coding no colour coding

(6) 2004/5 LCC Target < Met Average 2004/05 = or > Met Average and = or > Met Top Quartile target 04/05 < Met Top Quartile target 04/05

(7) % Gap between 2004/05 Met Top Quartile and LCC 2004/5 target LCC 2004/5 target below Met not used LCC 2004/5 target = or > Met Top (calc: 04/05 met TQ target - 04/05 LCC target / 04/05 LCC target *100) Top Quartile target Quartile target

(8) January 2004/05 target no colour coding no colour coding no colour coding

(9) January 2004/05 actual < January 2004/05 target not used = or > January 2004/05 target

(10) (Jan) 2004/05 (Month) 04/05 Forecast Yearly outturn < LCC 2004/5 target not used = or > LCC 2004/5 target

(11) January 2004/05 % improvement between 2003/4 LCC actual and negative change no change positive change (Month) 04/05 Forecast Yearly outturn (calc: 03/04 actual - 04/05 Forecast yearly outturn / 03/04 actual *100)

Scrutiny & Best Value Service 24/02/2005 13:59:45 Colour Coding Red Amber Green Page 1 of 4 Performance Plan PI Report by Committee - January 2004/05

Resource Select (1) (2) 3) (4) (5) (6) (7) (8) (9) (10) (11) Ranking Description 2003/4 LCC % 2004/5 Met 2004/5 LCC % difference Jan 04/05 Jan 04/05 (Jan) 04/05 % Comments Projection Actual Outturn improvement Top Quartile Target between Top Target Actual Forecast improvement LCC Outturn Target Quartile Target Yearly outturn on 03/04 Actual

AED Eric Wilkinson

Service Exchequer Management

BV8 The % of invoices for commercial goods and services which were paid by the authority within 30 days of such invoices being received by Higher figures are better Monthly /Critical the authority

87% +7.3% 93% +2.4% 91% 79.06% 90% +3.4% Monthly target not reached. Suppliers continue to be contacted to ensure they do not supply goods/services without an official purchase order. EMS currently processing invoices which are received in a "condition to pay" seven working days before settlement date.

AED Graeme Creer

Service Legal Services

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Performance IndicatorsReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Performance IndicatorsThis decision
  2. Key Performance IndicatorsNoted
  3. Key Performance Indicators for Children's Social CareAgreed
  4. Performance Management Database - various performance indicatorsAgreed
  5. Neighbourhood Performance IndicatorsNoted
  6. Neighbourhood Performance IndicatorsAgreed

More from Liverpool Resources Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
5 Apr 2006 Minutes of the Last MeetingsAgreed that the minutes be approved. Agreed Open
5 Apr 2006 Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... Agreed Open
5 Apr 2006 Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... Agreed Open
5 Apr 2006 Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. Agreed Open
5 Apr 2006 Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... Agreed Open