CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council

Leaf Fall Programme Review 2004/05

Agreed Committee 1 paper

Regeneration & Environment Select Cttee 2005/2006 agreed this item on Thursday 14 April 2005. Below is the council's own wording, with the papers it was decided on.

Item74

Resolved

Agreed that the information be noted and the appropriate officers be thanked for the substantial improvement made in the clearance programme.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Regeneration & Environment Select Cttee 2005/2006, 4 pages

Recommendation

That the contents of this Briefing Note be noted.

Background

Leaf Fall Clearance Programme 2004/05

3.1The primary purpose of the service is to remove fallen leaves in a timely and safe manner using a defined route and programme utilising a distinct body of operatives and resources. The programme for 2004/05 built upon the success achieved during the first leaf fall programme and also addressed some of the issues which identified following the review undertaken in January 2004

3.2The Leaf Fall Clearance Programme for 2004/05 commenced on the 20th September 2004 for 14 weeks and ended week commencing 29th December 2004. The programme started earlier than the first programme implemented by Enterprise Liverpool and ran 2 weeks longer.

3.3A total of 27 operatives, were deployed on a full time basis to leaf fall clearance. Additionally, during October 16 operatives were seconded from the Highway Verge Units to support the operation. To ensure these resources were deployed correctly two dedicated supervisors were issued responsibility for the day to day coordination of the service.

3.4One of the main benefits introduced during 2003/04 was the introduction of the leaf fall enquiry subject code which allowed Liverpool Direct Staff to code specific enquiries relating to fallen leaves direct, focusing the attention of Enterprise Liverpool support and operational staff in their response. Due to the absence of such a code the service was previously unable to compare performance for this area. Now this base data is available certain elements of performance can be compared. Appendix 1 compares the volume of leaf fall enquiries and the tonnages collected during the leaf fall programmes for 2003/04 and 2004/05.

4.0Programme of Work

4.1The programme of work comprised of specific gateway /corridor sites and residential sites. Gateway and corridor routes were programmed for weekly visits, while residential sites were visited fortnightly. The programme encompassed some flexibility in order that weather conditions and identified priorities could be dealt with. In addition specific feeder routes were added to gateway routes for 2004/05 and subsequently attract a weekly visit. These routes would typically link residential roads with main gateways.

The hours of work for gateways areas were between 4.15am and 11.30pm. Whilst more traditional sweeping times of 8am to 4pm were adopted for residential areas.

The programme locations were based on E-L Supervisors local knowledge of the areas in question based on subjective historical data. In addition some locations were identified utilising mapping data relating to tree locations on the highway.

4.2Resource Allocation

Resource allocation included:-

• Scarab Merlin Vehicles (Large) • Scarab Minors (Small) • Johnson C40 (Small) • Cage Wage • Skip Vehicle • Trilo Tractor Specialist Leaf Collection (Central Reservation Collection) • Leaf blowing equipment • Collection Skips

4.3Improved Methods of Working

The process for leaf collection on the gateway and corridor routes focused on operatives utilising leaf blowing equipment forcing leaves off the footpath into their collection path on the carriageway. In addition the trilo tractor was deployed to remove all leaves from grassed central reservation areas equally supported by operatives utilising leaf blowing equipment.

The data presented in Appendix 1 clearly identifies from the tonnage collection data that leaves were collected 17% quicker than the previous year. This is further supported by the reduction in enquiries a drop of over 50% from 2003/04 levels of 558 to 242 for 2004/05.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leaf Fall Programme Review 2004/05Report 4 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 25 attended
EC
Councillor Eddie CleinChair, present
SM
Councillor Steve MunbyDeputy Chair, expected
PB
Councillor Paul BrantMember, present
JC
John CoyneMember, present
KF
Councillor Kevin FirthMember, present
SM
Councillor Stuart MonkcomMember, present
BO
Councillor Bob OusbyMember, present
RR
Richard RobertsMember, present
PA
Councillor Peter AllenAlternate, in attendance
IJ
Councillor Ian JoblingMember, present
NS
Councillor Nick SmallMember, present
LS
Councillor Laurence SidorczukAlternate, present

All 25 on the meeting page

On this subject at Liverpool

Search all
  1. Leaf Fall Programme Review 2004/05This decision
  2. Council Motion - Leaf Fall Collection Service in Liverpool 18 by Councillors Tom Morrison, Erica Kemp and Richard Kemp CBEAgreed
  3. Leaf Fall Collection ProrammeAgreed
  4. Leaf Fall Clearance ProgrammeAgreed
  5. Enterprise-Liverpool - Leaf Fall Collection ProgrammeAgreed
  6. Motion - Leaf FallAgreed

More from Liverpool Regeneration & Environment Select Cttee 2005/2006

All decisions
MeetingDecisionOutcome
30 Mar 2006 Neighbourhood Management Boundary Review - PresentationAgreed that – (a) the report and the views expressed by Members be noted and taken into consideration in the preparat... Agreed Open
30 Mar 2006 Liverpool Plus - Strategic Investment FundAgreed that (a) the report be noted; and (b) a further report be submitted to the Committee in due course Agreed Open
30 Mar 2006 Annual ReportAgreed that the annual report of the Select Committee for 2005/06 be noted. Agreed Open
30 Mar 2006 Carbon Dioxide EmissionsAgreed that (a) the report be noted; and (b) a further report be submitted in 6 months time to include - · the progre... Agreed Open
30 Mar 2006 Response to Council Motion - Pedistrian Crossing Muirhead AvenueAgreed that a report on the results of the traffic survey be submitted to the appropriate Neighbourhood Committee as ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies