Resolved that approval be given for - (i) a virement of general capital resources of £326,228 from the minor highway works and bridge provisions programme lines in the 2004/05 Transportation Capital Programme to the Approach A580 budget; and (ii) the commitment of the additional expenditure of £326,228
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
(i) To update Members on progress on the A580 East Lancs Road / Lower Lane Junction Improvement and to provide commentary as to why the overall cost of the scheme is greater than originally forecast.
(ii) To seek approval to adjust the City Council’s Capital programme in order to take account of this overspend.
Executive Member/Director recommendation. Councillors Peter Millea and Keith Turner: Charlie Parker / Phil Halsall
That Members approve:
i) A virement of general capital resources of £326,228 from the minor highway works and bridge provisions programme lines in the 2004/05 Transportation Capital Programme to the Approach A580 budget.
ii) The commitment of the additional expenditure of £326,228 Key Decision?
Yes
Forward Plan
No – Appropriate notices will be published in accordance with the constitution
Implementation effective from:
9 May 2005
Timescale for action:
Immediate.
Reason(s) for Recommendation:
To adjust the capital programme to reflect increased costs of the East Lancs Road / Lower Lane Junction Improvement.
Alternative options to be considered:
Value Engineering has taken place to reduce expenditure on soft landscaping.
Consultation
GONW – ERDF Updates Regeneration Finance
Financial implications
The funding for this is being provided through a combination of ERDF grant and City Council General Capital Resources. The approved 2004/05 budget is as set out below.
Funding Source 2003/04 2004/05 Total Expenditure Budget Available Funding
ERDF 281,000 619,000 900,000 General Capital Resources 507,000 531,000 1,038,000 Total Funding Approved 788,000 1,150,000 1,938,000
Due to a series of cost overruns (which are detailed in Appendix 1), the original contract value has increased from £1,122,186 to £1,540,660, an increase of £418,474. There have however been some variances in the costs that were anticipated for charges from public utilities and also design fees from 2020 Liverpool, which have produced a reduction in those elements of the scheme cost of £92,246. The net position is an increase in the overall scheme cost to £2,264,228, £788,000 of which was financed in 2003/04. The approved budget for the project is £1,150,000 in 2004/05 leaving an unresourced total expenditure of £326,228.
As it is not possible to claim additional ERDF grant to finance all/part of the overspend, it will have to be financed by City Council general capital resources.
Hence, in order to finance this overspend, Members are therefore requested to approve the virement of general capital resources of £326,228 from the minor highway works (£153,228) and bridge provisions programmes (£173,000) budgets in the 2004/05 Transportation Capital Programme to the Approach A580 SIA budget. £153,228 from the minor works programme represents resource which was originally assigned to works in the SIAs but was vired in the 3rd quarter review to take account of slippage in SIA infrastructure projects. Consequently its transfer to the A580 project in the SIA will not reduce the overall budget for minor works approved in the Transportation Capital Programme set out in report No FMS 22 04 of 22nd March 2004. The £173,000 for bridge maintenance represents slippage in projects which will now occur in 2005/06.
Best Value:
The works were tendered through City Council procedures. A shortlist of six contractors were invited to tender on a wholly price basis.
Furthermore a number of ‘Value Engineering’ exercises have taken place throughout the project, the purpose of which were to minimise the overspend on the project.
Equality implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.