CCMS - City Centre North Package 1 - Conversion of footpaths to shared use, unsegregated pedestrian/cycle routes
DecidedCommittee4 papers
Highways and Public Spaces Representation Committee 2020/21 decided this item on Monday 20 June 2005. Below is the council's own wording, with the papers it was decided on.
Resolved that: (a) Having considered the report of the Highways Manager and read the written objections to the scheme the Committee decided to adjourn the meeting pending officer consultation with the School for the Blind and Liverpool Voluntary Services for the Blind. (b) The resumed meeting to take place following the rising of the Executive Board after consultation with the above groups. The meeting was resumed at 10:30am on Friday 29 th July 2005.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Highways and Public Spaces Representation Committee 2020/21, 9 pages
Purpose of report
To consider the comments received on the proposed conversion of footways into unsegregated pedestrian / cycle routes on Byrom Street, Hunter Street, Leeds Street, Edgar Street, Christian Street and Byrom Way. The proposals are part of the City Centre North Package 1 Project (City Centre Movement Strategy).
Recommendation
That the comments be noted, but that the Highways Manager be granted approval to implement the Footway Conversion as part of the City Centre North Package 1 Project.
INFORMATION
Background
1.1The broad principles of the City Centre Movement Strategy (CCMS) were the subject of public consultation in 2000 and were strongly endorsed. Further details of the proposals and an outline programme were consulted upon in November 2003, and the agreed strategy has become a fundamental part of the City Council’s Regeneration Programme.
1.2The principle objectives of CCMS are summarised below;
• To improve accessibility to the City Centre to aid economic regeneration and to provide access for all; • To create a people friendly City Centre that is safe, clean and attractive for work, shopping, business tourism and leisure; • To make best use of the City Centre’s key transport assets – the Merseyrail Stations, bus facilities, ferries and major car parks; • To support the improvement of the City Centre’s architecture and townscape; • To ensure that measures can be funded and implemented;
1.3To realise these objectives, a primary aim of CCMS in the north of the City Centre is the removal of excess traffic from Dale Street, and its accommodation on the more appropriate radial routes, (Hunter Street, Byrom Street and Leeds Street). The City Centre North (CCN) Package 1 Project takes the first step in achieving this objective by;
• Improving the Hunter Street / Byrom Street Junction to better deal with the increase in traffic. • Converting Tithebarn Street to two-way working, providing improved access to the northern parts of the City Centre, including the growing Commercial District.
1.4Recently completed CCMS schemes include the repaving of the Covent Garden and East Moorfields Areas, (Package Y); the repaving of the Cavern Quarter and Williamson Square Areas including the new fountain in Williamson Square, (Package X); and the introduction of improved pedestrian signing around the City Centre, (Connecting Liverpool).
1.5CCMS schemes currently under construction include the Renshaw Street / Berry Street Mixed Priority Route; the Hunter Street / Byrom Street Junction Improvements; and the Tithebarn Street Corridor Improvements (the latter two collectively known as the CCN Package 1 Project).
1.6The details of the CCN Package 1 Project were the subject of a public information exercise in April 2004. The proposals included the conversion of a number of existing footpaths into shared use, unsegregated pedestrian / cycle routes. All the footpaths in question are in the vicinity of the Hunter Street / Byrom Street Junction Improvements which are currently on site. The exact locations of the footpaths are identified on the Plan in Appendix A.
1.7Conversion of an existing footpath into a shared use, unsegregated pedestrian / cycle route does not require a Traffic Regulation Order. However, under Sections 66(4) and 65(1) of the Highways Act, Local Authorities are required to erect, and maintain for a period of 28 days, in the vicinity of the affected footpaths, “Notices of Intent” of the proposed conversion. Comments are invited during this statutory 28 day period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Highways and Public Spaces Representation Committee 2020/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.