Resolved
That the Local Transport Plan – Annual progress report for 2005 be endorsed for submission to the Department for Transport.
Merseyside Strategic Transportation Committee decided this item on Friday 1 July 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Local Transport Plan – Annual progress report for 2005 be endorsed for submission to the Department for Transport.
1.1The first Local Transport Plan (LTP) is now in its final year of delivery and continues to identify, fund and deliver integrated transport solutions to tackle social, economic and environmental issues across Merseyside.
1.2As Members are aware, Annual Progress Reports (APRs) are required each year by the Department for Transport (DfT) as a means of reporting on progress of the LTP.
1.3The APR for submission this year covers the 2004/05 financial year. DfT is strongly encouraging authorities to submit their APRs at the end of June, as opposed to traditional deadline of the end of July, in order to allow time for DfT to address any issues of conflict or ambiguity within the submission ahead of its final assessment. Following a discussion with GONW, the Merseyside authorities are being allowed to submit on the 1st July, to allow time for MSTPC to note the submission at today’s meeting.
1.4It is fully appreciated that timescales are very tight, as always, but it is important to clarify that the APR is a retrospective accounts of LTP delivery. It does not constitute new transport strategies or funding packages. The second LTP (the subject of a separate presentation) will set out the provisional strategy for future years.
1.5This year’s APR is also required by Department for Transport to be a short, simple document aimed at conveying technical information in graphical and tabular format. It focuses on the following:
• Progress towards targets and objectives • Scheme delivery and LTP spending (including maintenance data) • Progress on major schemes
1.6As in previous years, Merseyside’s Strategic Transportation and Planning Committee (MSTPC) is requested to note and give its endorsement to the APR. However, the APR is also being reported to the partner authorities individually by means of Executive Board or Executive Member briefings, as appropriate. 1.7 A more detailed “super APR” is required by DfT in July 2006, to report on overall progress in delivery the first LTP. This will be developed in close consultation with members of MSTPC.
2 Key messages contained within the APR
2.1The APR builds on the success of last year’s report, which was received favourably by the Government. Work has continued on delivering the strategy, including work on the major schemes.
Spend and delivery
2.2In the 2004 APR, the authorities committed themselves to a capital programme of £64.159m to cover integrated transport and maintenance. £ 63,686m has been spent on transport schemes.
2.3All supplementary funding awarded for the development of the Strategic Investment Areas and the City Centre Movement Strategy was spent on eligible works within these areas.
Performance targets
2.5This year’s APR will emphasise the good progress which has been made towards many of the LTP’s performance indicators.
Major schemes
2.6Liverpool South Parkway. Work commenced on site in July 2004 and is progressing well. The new facility is programmed to open in June 2006
2.7Merseytram Negotiations regarding the scheme are still progressing but it is not possible to report any further detail at this stage.
2.8Blackbrook Diversion This St Helens scheme already has ‘provisional approval’ and the up- dated assessment required to obtain ‘full approval’ has been submitted to the DfT with the anticipation of receiving approval to start in 2006/07.
2.9Looking at other major schemes, the fact that Hall Lane Gateway scheme is no longer recognised by DfT as an immediate priority for funding is of great disappointment to LCC and the LTP partners. This will be reflected in the APR submission. Notwithstanding this, excellent progress with delivery can be reported over the 2004/05 year, including the submission of a planning application for the works, the making of a Side Roads Order and a Compulsory Purchase Order.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LTP Annual Progress Report 2005Report | 3 pages | DownloadRead as text |
Follow Merseyside Strategic Transportation Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Feb 2012 | Minutes of Last MeetingAgreed that the minutes of the last meeting held on 2 November 2011 be approved as a correct record. Matters Arising:... | Agreed | Open |
| 8 Feb 2012 | Local Sustainable Transport Fund UpdateAgreed that the report be noted and that further updates be provided to the Committee as required. | Agreed | Open |
| 8 Feb 2012 | Local Enterprise Partnership (LEP) UpdateAgreed that the report be noted. | Agreed | Open |
| 8 Feb 2012 | Terms of ReferenceAgreed that the proposed revised for the Committee be approved for implementation with effect from 8 February 2012. | Agreed | Open |
| 8 Feb 2012 | Schedule of Meetings 2012Agreed that , noting the Local Enterprise Partnership will adopt a revised sequence of meetings to that indicated, th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.