Resolved
Agreed that a Development Meeting be arranged as soon as possible to consider the plan in detail.
Garston Neighbourhood Committee agreed this item on Thursday 20 October 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that a Development Meeting be arranged as soon as possible to consider the plan in detail.
SOUTH LIVERPOOL NEIGHBOURHOOD MANAGEMENT AREA
NEIGHBOURHOOD RENEWAL DELIVERY PLAN (2005/06)
City of Liverpool
1 Contents
Part A - Introduction and Regeneration Context
Introduction
1. Regeneration Context of the South Liverpool area - Spatial Characteristics - Policy Focus - Major Projects and Investments - Priorities identified by stakeholders
2. Progress under the Neighbourhood Action Fronts - (i) Employment - (ii) Crime - (iii) Education - (iv) Health - (v) Housing and Liveability - (vi) Inclusive Communities
3. Community Engagement/Community Charter
4. Governance/Performance Management
Part B – Performance Management Framework/Delivery Schedule
2 Part A – Introduction and Regeneration Context
Introduction
Liverpool Partnership Group (LPG) has commissioned the production of Neighbourhood Renewal Delivery Plans for the 7 Neighbourhood Management Areas in the City. The purpose of these plans is to demonstrate the impact of LPG’s actions at a local level on the Neighbourhood Renewal Floor Targets.
The Plan has been developed by the South Liverpool Neighbourhood Management Service following consultation with the Board of the South Liverpool Partnership and LPG Strategic Issue Partnerships. This document builds upon the 2004/05 Neighbourhood Delivery Plan and sets out those key actions partners will be delivering to meet local targets across the NMA over coming years. These targets derive from the national Public Service Agreement (PSA) Targets set by central Government and Liverpool’s Local Strategic Partnership, as laid out in the city wide Community Plan and integrated NRS Target Action Plan.
The plan builds on the work of the local community groups and partners that form the South Liverpool Cluster Partnership, and sets out how the updated Neighbourhood Renewal Strategy (NRS) will be delivered across the South Liverpool Partnership Area. The responsibility for delivery is shared among those partners, and this document aims to offer a clear point of reference as to who is doing what.
South Liverpool NMA falls within the city council wards:
Speke-Garston
Allerton & Hunts Cross
Woolton
Belle Vale
The Delivery Plan consists of two parts:
Part A – Introduction and Regeneration Context
Reflecting on the strategic regeneration context of the area including progress made to date and a look forward to the challenge of the two years ahead, this section sets out the key focus for the South Liverpool Area over the next 12 months.
Part B – Performance Management Framework/Delivery Schedule
A detailed schedule of actions focusing on PSA Targets and key local priorities. Targets/actions have been developed at a Neighbourhood Management Area level, while also illustrating the impact and outcome of floor targets at ward level.
3 1 Regeneration Context of the South Liverpool area
Figure 1 - Map showing the South Liverpool area – Wards
∗ CHILDWALL
BELLE VALE
WOOLTON CHURCH
ALLERTON AND HUNTS CROSS
CRESSINGTON
SPEKE GARSTON
© Crown Copyright. All rights reserved The City of Liverpool, 100018351, 2005
4 Spatial Characteristics
Location
1.1The South Liverpool Neighbourhood Management Area stretches for several miles along the Mersey beyond the older suburbs of Liverpool to the rural fringe of the city. The urban fabric is a mix of established Victorian streets around Garston, the large inter-war/post-war ‘ garden-suburb’ satellite town of Speke and the ‘Radburn’ type housing of the 1960s and 70s municipal estate at Netherley.
1.2Residential tenures of all kinds can be found in each neighbourhood location but tend to be in high concentrations of a single principal type, with the social rented sector in the majority overall. Garston is the most mixed area in terms of tenure and uses, retaining an ‘urban village’ character.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Neighbourhood Delivery Plan: South LiverpoolReport | 49 pages | DownloadRead as text |
Follow Garston Neighbourhood Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Apr 2008 | Minutes of the Last MeetingAgreed that - a) It be noted that a report following consideration of Minute 44 (Programme for a Clean Neighbourhood ... | Agreed | Open |
| 24 Apr 2008 | Spotlight Topic - Parks and Open SpacesAgreed that – a) Derek Dottie be thanked for the detailed information and assessment of performance which was present... | Agreed | Open |
| 24 Apr 2008 | Garston Regeneration – The Next Phase (NH/24)Resolved that the recommendation as amended in respect of paragraph (ii) above be approved subject to the deletion of... | Approved | Open |
| 24 Apr 2008 | Emissions at Garston DocksAgreed that the information be noted and all parties be thanked for their frank and honest contributions to the discu... | Agreed | Open |
| 24 Apr 2008 | Neighbourhood Manager's ReportAgreed that – a) The contents of the report and the update in relation to Garston Urban Village Hall, be noted; and b... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.