Resolved that the following be approved - (i) acceptance of £25,000 external funding from the Environment Agency to support expenditure on Greenbank Park Lake; (ii) acceptance by the City Council of the role of accountable body for the Environment Agency Grant; (iii) the Manager for Parks and Environment be appointed as the nominated officer for monitoring compliance with the terms and conditions the grant. (This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises); (iv) an amendment to the Capital Programme to incorporate additional expenditure of £25,000 on Greenbank Park, financed by grant; and (v) the commitment of the expenditure.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
To accept a grant of £25,000 the Environment Agency and include this funding in the 2005-06 Capital Programme with commitment to spend.
BACKGROUND The Environment Agency (EA) has a duty to promote the sustainable use of water and associated land for recreational purposes where this will not adversely impact on people or wildlife. The EA seeks to work in partnership with other organisations which share complementary interests. Over the past 5 years, the Environment Agency has been working in partnership with Liverpool City Council and assisting with funding on park lakes. In 2003-04, the Environment Agency funded a thorough report into the condition of Greenbank Park Lake and in 2004-05 the first phase of associated improvements commenced, with LCC funding supported by a further £25,000 from the EA. The work primarily addressed the problem of bank erosion in a sensitive manner using piles made from recycled plastic. This approach helped to secure a Green Flag Award for the park earlier this year but, owing to unforeseen ground conditions, the cost of the Phase 1 works was £9,900 more than anticipated. An extra £25,000 has now been made available by the EA to settle the additional costs and for a second phase of improvements to Greenbank Park Lake including the provision of fishing pegs.
1) Acceptance of £25,000 external funding from the Environment Agency to support expenditure on Greenbank Lake Park;
2) Acceptance by the City Council of the role of accountable body for the Environment Agency Grant; 3) The Manager for Parks and Environment is appointed as the nominated officer for monitoring compliance with the terms and conditions the grant. (This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises);
4) An amendment to the Capital Programme to incorporate additional expenditure of £25,000 on Greenbank Park, financed by grant; and
5) The commitment of the expenditure.
Key Decision?
No.
Forward Plan?
Yes.
Implementation effective from:
4 November 2005.
Timescale for action:
November 2005.
Reason for recommendation
To fund existing obligations and future park improvements.
Alternative options to be considered:
None.
Consultation
Regeneration Finance (Anne Ryans), Regeneration (Mark Smith) Parks and Environment (Paul Scragg).
Consultation with Ward Councillors and outcome:
Ward Councillors were consulted and gave their support prior to commencement of the lake improvement works. Owing to financial constraints, certain approved works were deferred. The additional funding presently offered by the Environment Agency will allow a further phase of the approved scheme to be constructed. Financial implications:
The Capital Programme for 2004/05 allowed for essential lake infrastructure works at Greenbank Park in the sum of £82,000. Of this sum £25,000 was provided by the Environment Agency and £57,000 was financed by City Council general resources. Owing to difficult ground conditions progress on site was slower than anticipated and during 2004/05 a total of £30,000 was spent on the first phase of improvements to the Greenbank Park Lake. Of this sum, £5,000 was financed by City Council general resources and £25,000 by the grant from the Environment Agency.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.