Overview and Scrutiny Select Committee 2005/2006 agreed this item on Tuesday 8 November 2005. Below is the council's own wording, with the papers it was decided on.
Agreed that – a) the presentation be noted b) the recommendation detailed in the report, suggesting that corporate risks and associated risk treatment measures be reported to the Overview and Scrutiny Select on a quarterly basis and the full City Council annually, be approved; and c) each Select Committee be requested to review their individual portfolio Corporate Risk Registers on a quarterly basis, and the work programmes be amended accordingly
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Overview and Scrutiny Select Committee 2005/2006, 13 pages
Corporate Risk Register 31/10/05
Assessment of Risk [As it is now] Risk Control Assessment of Residual Risk [With Responsible Timescale/ control measures implemented] Risk Measures Review Definition of Risk Likelihood Impact Risk Score Likelihood Impact Number (Probability) (Severity) (Probability) (Severity) Residual Risk Score [L] [I] [ I x L] [I] [L] POLITICAL That an accurate Chief Ongoing assessment of the Executive capacity of the organisation be The Council agrees made prior to the policies and projects at a inception of each P1 3 3 9 2 2 4 pace that the organisation new policy or cannot match project and that the assessment be shared with members
That consultation Chief Ongoing procedures prior Executive There is no agreement to the establishing P2 with local stakeholders on 3 3 9 of new priorities 2 2 4 local priorities are adequate to minimise conflict
Council's Aims Chief By 31/12/2005 and Objectives Executive clearly stated. Executive Board do not All new initiatives P3 2 3 6 1 3 3 own change agenda more clearly related back to Council's Aims and Objectives. Establish regular Chief By 31/03/2006 Conflicts and tensions liaison meetings Executive P4 between LCC and major 2 4 8 and disputes 1 4 4 partners resolution procedure
Page 1 of 13 Corporate Risk Register 31/10/05
Assessment of Risk [As it is now] Risk Control Assessment of Residual Risk [With Responsible Timescale/ control measures implemented] Risk Measures Review Definition of Risk Likelihood Impact Risk Score Likelihood Impact Number (Probability) (Severity) (Probability) (Severity) Residual Risk Score [L] [I] [ I x L] [I] [L] Improve Chief ongoing consultation Executive arrangements City wide and council between priorities not informed by communities and P5 local needs and priorities 3 3 9 2 2 4 local stakeholder identified by communities groups to inform and local stakeholders Council Policies, objectives and decisions GOVERNANCE Arrangements are Chief Ongoing made to include Executive Decision making does not the views of adequately take into Neighbourhood G1 account the visions of 3 3 9 Committees when 2 2 4 Neighbourhood decisions are Committees made
Improve Chief Ongoing governance Executive Governance processes arrangements - are by-passed in order to including G2 "get results" but resulting 3 3 9 understanding in 1 3 3 in adverse effects upon advance legal, the City Council financial and risk implications of all new initiatives Members outside the Strengthen Executive By 31/03/2006 Executive Board, scrutiny, through Director particularly those on the appropriate work Resources G3 2 3 6 1 3 3 Select Committees, do not programmes, understand, accept or member training perform their roles MANAGERIAL / PROFESSIONAL
Page 2 of 13 Corporate Risk Register 31/10/05
Assessment of Risk [As it is now] Risk Control Assessment of Residual Risk [With Responsible Timescale/ control measures implemented] Risk Measures Review Definition of Risk Likelihood Impact Risk Score Likelihood Impact Number (Probability) (Severity) (Probability) (Severity) Residual Risk Score [L] [I] [ I x L] [I] [L] That the Executive Ongoing embedding of risk Director An unanticipated management Resources M1 2 4 8 1 3 3 significant risk arises across all areas of the Council be implemented Improve the Executive By 31/12/2005 technical support Director available to Resources change initiation and project teams Large scale initiatives lead by establishing a M2 to unforeseen adverse 2 4 8 1 3 3 technical referral impacts panel of officers/partners with relevant expertise
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
Annual Report - Overview and ScrutinyAgreed that – (a) the information be noted; and (b) the report be produced in a glossy, user friendly, easy to unders...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.