Resolved
Resolved that the City Council approves entering into an agreement with BT and authorise the Assistant Executive Director (Treasury and Risk Management) to make arrangements for the contract to be signed.
Executive Board approved this item on Friday 25 November 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the City Council approves entering into an agreement with BT and authorise the Assistant Executive Director (Treasury and Risk Management) to make arrangements for the contract to be signed.
The initial Microconnect Distributed Antenna (MDA) report was submitted to Customer and Corporate Select Committee on 30 June 2005, approved by Executive Board on 22 July 2005 and called in to Customer and Corporate Select Committee on 18 August 2005 where it was endorsed. The report outlined the proposal from British Telecom to establish an MDA system which is complimentary to existing mobile phone infrastructure and designed to be shared by up to five mobile operators. Its purpose is to provide enhanced coverage and extra capacity in the city centre. The discreet nature of MDA installations and the fact that they utilise existing street furniture such as lamp posts and CCTV structures, will ensure the installations are of minimal environmental impact.
The purpose of this report is to set out the main points of the agreement and seek approval for this new partnership arrangement with BT.
Proposition
A contractual agreement between BT and the City Council for eight years is proposed. This will cover the installation and maintenance of MDA initially across a 4 square kilometre area of the city centre to provide blanket 3G mobile phone coverage. The existing 2G mobile phone coverage will also be supported by this network. The installation of MDA will not exceed 1% of the City Council’s street lighting stock.
The proposed agreement with BT does not limit installation of MDA to the city centre and if required officers will refer any request by BT to expand beyond the city centre area back to members to consider. However should members decide not to approve a location and BT does not agree with that decision the matter will be dealt with under the dispute resolution provision set out in the agreement and referred to a mediator or ultimately the courts to decide.
The rent paid by BT for use of street furniture to house MDA will be £1,000 per installation per year. This will be reviewed after 5 years and the subsequent income should not be less than the compound Retail Price Index over this period.
Consultation with residents and businesses in close proximity to the proposed MDA sites will be undertaken prior to deployment of MDA by BT. The Highways Safety Officer will visit each of the proposed MDA sites prior to installation and evaluate the appropriateness of the locations.
Executive Member/Director recommendation (Councillor Dave Antrobus / Phil Halsall)
1. That the City Council approve entering into an agreement with BT and authorise the Assistant Executive Director for Treasury and Risk Management to make arrangements for the contract to be signed.
Key Decision
Yes.
Forward Plan
No. – Appropriate Notices will be served
Implementation effective from
16 December 2005
Timescale for action
Immediate.
Reason(s) for Recommendation
To explore ways of delivering effective mobile technologies to the people, organisations and business of Liverpool which minimise impact both environmentally and within communities. Alternative options considered
None.
Initial consultation has been undertaken with the following services: • Financial Management • Legal Services • Procurement Unit • Highways Management • Development Control
Income of £1,000 per MDA installation for each year of the contracted period of 8 years. Subject to review after 5 years. Start up costs to be charged against income.
Best Value
This is currently unique to BT. It is known that other local authorities are entering into similar agreements on similar terms
None.
Corporate strategy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Microconnect Distributed Antenna (C&CS/7)Report | 4 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.