Resolved
Agreed that the information be noted and each Select Committee be requested to consider the entries which relate to their particular service areas.
Overview and Scrutiny Select Committee 2005/2006 agreed this item on Wednesday 1 February 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the information be noted and each Select Committee be requested to consider the entries which relate to their particular service areas.
NEW ENTRIES IN THE FORWARD PLAN
February – May 2006 ___
COUNCILLOR PETER MILLEA
EXECUTIVE MEMBER
_____
REGENERATION _____ WARD Central
Title of report Decision to be taken by and approval process Pier Head Public Realm Improvements Executive Board on the recommendation of Councillors Peter Millea Executive Member for Regeneration and Keith Turner Executive Member for Resources
Decision, background and implications
The report will seek approval to proceed to detailed design on the proposed improvements to the Public Realm at Pier Head with a view to submitting applications to secure funding to implement the project. It is important to proceed with this project to ensure delivery of improvements at Pier Head to tie in with the implementation of the Liverpool Canal Link in advance of 2008. The site is at the heart of the World Heritage Site and Mersey Waterfront and is an important gateway to the City. It is a key decision as this work is valued at £320,000 with funding already secured from City Focus and British Waterways
Date to be Submitted to Select Committee
The report will be referred to select committee if considered appropriate by Executive Board
Consultation with Ward Councillors and Neighbourhood Committees
Ward Councillors have had written details, the Neighbourhood Committee have been consulted in respect of the planning applications for the waterfront projects
Consultation with the public/partner agencies
Consultation will be ongoing during the detailed design phase with local stakeholders including adjacent landowners and building owners, Mersey travel and the Federation of Waterfront Residents
Availability of Documents and how to submit any view you may have about the proposal
Pre decision papers are available from, and views on the proposal should be submitted by 1 February 2006 to; Name: Rosey Paul Designation: Project Manager, City Centre Projects Team Address: Municipal Buildings, Dale Street Email: [email protected] Tel: 0151 225 3735. WARDS Riverside, St. Michaels, Mossley Hill
Title of report Decision to be taken by and approval process
Proposed Transport Study – Sefton Executive Board, on the Street, Riverside Drive and Jericho recommendation of Councillor Peter Lane (“Riverside Drive Corridor”) Millea, Executive Member for Regeneration.
Decision, background and implications
To note the intention to conduct a transport study to identify future transport requirements on the corridor, and to approve a policy that developer contributions (to be secured as planning obligations) be sought as a primary source of funding for improvements identified as a result of the study. The corridor to be studied includes three wards hence this is a key decision.
The study will initially involve the production of a microsimulation transport model and will include an assessment of baseline transport conditions, consideration of committed schemes/developments, effects of background traffic growth, and effects of potential developments. Various options to cater / mitigate for future predicted demand for travel can then be tested.
It is proposed to fund the work as an extension to the Southern Corridor Study, funding for which is in the approved Capital Programme.
Date to be Submitted to Select Committee The report will be referred to the Select Committee if considered appropriate by the Executive Board.
Consultation with Ward Councillors and Neighbourhood Committees
Riverside, St. Michaels and Mossley Hill Ward Councillors will be advised of the study on its approval by Executive Board. Any recommendations and/or proposals arising from the study will be referred to Ward Councillors and progressed to Neighbourhood Committees as appropriate.
Consultation with the public/partner agencies
Any recommendations and/or proposals arising from the study will be subject to consultation as appropriate, in accordance with the consultation strategy.
Consultation Strategy Compliance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Forward Plan: New EntriesForward_plan | 39 pages | DownloadRead as text |
Follow Overview and Scrutiny Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Apr 2006 | Minutes of the Last MeetingAgreed that the minutes of the Select Committee of 1 February 2006 be approved as a true record. Matters Arising Minu... | Agreed | Open |
| 4 Apr 2006 | Corporate Performance Plan 2005/06 3rd QuarterAgreed that - (a) the report be noted ; and (b) it be reiterated to all Select Committees that in order to tackle poo... | Agreed | Open |
| 4 Apr 2006 | Annual Report - Overview and ScrutinyAgreed that – (a) the information be noted; and (b) the report be produced in a glossy, user friendly, easy to unders... | Agreed | Open |
| 4 Apr 2006 | Forward Plan - New EntriesAgreed that - (a) in relation to the entry regarding the progress of the Housing Capital Programme Sue Mansfield be r... | Agreed | Open |
| 4 Apr 2006 | Revisions to Scrutiny Good Practice GuideAgreed that – (a) the revised scrutiny good practice guide be approved and submitted to the Annual Meeting of the Cit... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.