Highways and Public Spaces Representation Committee 2020/21 deferred this item on Monday 20 February 2006. Below is the council's own wording, with the papers it was decided on.
Resolved that having read the report and read and heard all of the objections put forward, the item be deferred in order that the following issues be addressed before receiving further consideration by the Committee: - (a) Completion of the cycling audit of the scheme; (b) Carrying out a capacity study in relation to the volume and physical weight of traffic which the scheme would produce along Georges Dockway , with particular reference to the effects of the increase of traffic upon occupiers of neighbouring premises; (c) Consideration of a scheme amendment to permit cyclists to continue to cross the Strand from Water Street to the Pier Head; (d) Consideration of a scheme amendment to provide a pedestrian controlled signal across the bottom of Chapel Street; (e) Consideration of a scheme amendment to permit cyclists to continue to make a left-turn from Strand Street into Mann Island to incorporate physical measure to prevent the turn’s use by other vehicles; and (f) Consideration as to the practical aspects of how the shared pedestrian and cycling facilities will operate with reference to pedestrian safety.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Highways and Public Spaces Representation Committee 2020/21, 21 pages
Purpose of report
To consider a report on representations received to the implementation of various prohibitions proposed along:
1. Strand Street / Goree 2. Brunswick Street
3. Georges Dockway
4. Mann Island
5. Water Street
Recommendation
That the representations are not sustained and the Highways Manager — Highways Management be granted approval to implement the proposed prohibitions.
1.0INFORMATION
1.1Members will be aware Liverpool City Council and _ its partners are currently engaged in a major regeneration programme. A key part of the regeneration is the introduction of The Strand Corridor Masterplan, the details of
1.2
1.3
2.0
2.1
2.2
2.3
which were presented to the Executive Board on the 30" July 2004.
The report detailed to Members the need to take a phased approach to delivering The Strand Corridor Masterplan due to budgetary constraints together with the relevant Traffic Regulation Orders (TRO’s) necessary to facilitate the control of traffic movement and where possible increase junction capacity by rationalising kerb side parking in the area.
The TRO’s are required specifically to accommodate the anticipated growth in traffic volume along the Strand. In addition, by regulating traffic demand in the area it is possible to improve pedestrian linkages between the City Centre and the Pier Head through the establishment of improved pedestrian crossings at key crossing points. This combination of regulation and infrastructure improvement will provide a better pedestrian environment, in support of future development, at Mann Island and Pier Head.
- BACKGROUND
The Masterplan for the Strand Corridor, presented to the Executive Board, identified major public realm works with extensive highway remodelling in support of the public realm improvements. The objectives of the Masterplan being to create high quality public spaces, improve pedestrian linkages between the City Centre and the Waterfront and the establishment of a traffic management system which can accommodate the anticipated growth in traffic volumes.
In the presentation to the Executive Board, it was identified not all of the Masterplan proposals could be implemented to the budget allocation therefore, a staged implementation would be necessary. It was proposed the first area to be improved be the length of The Strand / Goree between Mann Island / James St and Mersey Tunnel Exit.
Resulting from further budgetary constraints, it is now not possible to implement all of the Masterplan proposals for the area from Mann Island / James St to the Mersey Tunnel Exit. Current proposals meet some, but not all of the Masterplan objectives therefore the remaining proposals are to:- 2.4
3.0
3.1
3.2
3.3
« Accommodate the anticipated growth in traffic volume along the Strand.
e Improve the pedestrian linkages between the City Centre and Mann Island / Pier Head
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Highways and Public Spaces Representation Committee 2020/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.