Resolved that - (i) the proposal for a 50 metre pool at a cost of £14.9 million, the contract should be fixed price and managed through 2020, be approved; (ii) the awarding of the contract to Gleesons Building Ltd at the revised tender price of £14,363,599, be approved; (iii) the use of £10.7 million of unsupported borrowing towards the financing of this proposal be approved; (iv) additional revenue provision be included within the Leisure Services Revenue Budget for the cost of financing the unsupported borrowing of £0.353 million in 2006/07, and £0.685 million in each subsequent year, and that the additional budget be accommodated within the City Council’s overall Budget requirements for 2006/07 and future years; and (v) the issuing of a letter of intent in advance of contract exchange, be approved.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of this report is to confirm the revenue and capital funding for the provision and operation of the new Picton 50m swimming pool.
Background
Picton Sports Centre is located in Wavertree Playground and is the largest Council operated sports centre. It provides a large concentration of both indoor and outdoor sports facilities. These facilities are managed and operated as a single integrated complex, generating over 500,000 customer visits per year and is the only centre capable of hosting major multi-sports events and festivals
The two Victorian swimming pools have reached the end of their useful life and have been closed for over 18 months. The Council is in the process of finalising contracts with Gleeson Building Ltd to construct a replacement swimming facility on the Picton site in the form of a new 50m pool. The revised total capital cost for the new pool is now £14.9 million of which £4.02 million is to be funded from a Sports Lottery Grant.
The new pool complex will deliver for the City a full range of enhanced swimming opportunities. The new facilities will underpin the strategic aim of the City Council to provide high quality, sustainable and accessible water space. The pool will meet the needs of recreational swimmers, swimming clubs, community groups and provide facilities for schools to deliver their national curricular attainment targets for swimming. Swimming is widely recognised as one of the most beneficial physical activities and this pool will have a significant impact in improving the health of Liverpool residents through increased participation in healthy physical activity. The pool will also be used to provide enhanced learn to swim initiatives and as the centre of excellence for the delivery of the Councils swimming development and elite training programmes. The pool will be key to the potential success of Liverpool swimmers who will be preparing to compete for medals in the 2012 Olympics. The complex will provide the following :-
• A deck level 50 metre x 8 lane pool with a movable floor and dividing boom. • A second deck level 20 metre x 4 lane community / teaching pool also with a movable floor. • Spectator seating for 400. • New car park with CCTV and other crime prevention measures
However, in agreeing to include the new pool within the 2005/06 Capital Programme, the Executive Board required that a further report be brought forward before commitment could be entered into, that would demonstrate how the Leisure budget would meet the revenue funding of the new pool and the cost of servicing the Council’s capital contribution. However, Leisure Services have been unable to finance the capital repayments.
In the interim officers from the Resources portfolio have sought to reduce the Council’s capital contribution by linking this project to the capital allowances funding mechanism that is being used to fund the fit out of the Kings Dock Arena.
Whilst this approach was successful in identifying a possible cost reduction this is no longer possible as it required ‘qualifying’ expenditure to be incurred by the end of this tax year.
Information
Current Controllable Revenue Budget – Picton SC Based on current forecasts the controllable net subsidy budgeted for the complex is £636k (excluding capital repayments) and is made up as follows :
Total Complex Total expenditure for the complex £1,448k Total income for the complex £812k Total net subsidy for the complex £636k
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.