Extension Leeds Liverpool Canal (RES/2)

Approved Executive 1 paper

Executive Board approved this item on Friday 2 June 2006. Below is the council's own wording, with the papers it was decided on.

Item4a

Resolved

Resolved that – (i) the recommendation be approved; and (ii) the decision be referred to the Resources and Corporate Services Select Committee. RES/3
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 8 pages

Executive summary

This report has been prepared by 2020 Liverpool Ltd, to report the outcome of negotiations with British Waterways (BW) for the grant of a lease of land at the Pier Head to facilitate the construction and operation of an extension of the Leeds Liverpool canal.

Background

The proposal for the extension of the Leeds Liverpool canal into the Albert Dock was conceived about 10 years ago. Since then the idea has been developed by BW into firm proposals, planning permission has been obtained and finance raised.

Most of the canal extension runs through land owned by the Mersey Dock and Harbour Company (MDHC) and BW are in an advance stage of negotiations for the release of land required. The land to the south of the Port of Liverpool Building (Mann Island) is owned by National Museums and Galleries on Merseyside and BW is also in an advance stage of negotiation with them regarding this link of the canal.

The land at the Pier Head in front of the Three Graces is owned by Liverpool City Council and MDHC. The majority of land held by MDHC at the Pier Head is dedicated to public use through various agreements. The remainder of the land is owned by the City Council and is the subject of this report.

The Pier Head and surrounding area is a World Heritage Site. Current Position

Provisional terms have been reached with BW for an agreement for a lease and subject to the satisfactory completion of the works, the grant of a long lease. The lease will be for a term of about 140 years and be co-terminus with a lease to be granted by MDHC in respect of other parts of the canal. The agreement for a lease will permit BW to enter onto the site and carry out the construction of the canal. For the purposes of the agreement for the lease, the site will be the actual land required for the canal and the construction lay down areas that will extend for about 10 to 20 metres on either side of the line of the canal. The canal will be constructed in phases in order to retain public access to the river front, the Mersey Ferry and the restaurant. The precise area required for the construction lay down area and the phasing of the work has not yet been determined.

The proposed design of the canal at the Pier Head between Princes Dock and Canning Dock will comprise of a culvert except for two sections of open waterspace sited opposite the Liver Building and the Port of Liverpool Building. The two open sections of waterspace will be complemented with adjacent terracing. Issues regarding the relocation of statues, public access etc. and the provision of removable decking for the facilitation of larger public events have been dealt with in the planning consent and the BW are required to enter into a s106 agreement of the Town and Country Planning Act 1990.

In conjunction with the construction of the canal there are proposals for the improvement of the public open space at the Pier Head. Discussions are currently ongoing regarding the possibility of BW and/or BW’s contractors undertaking this work at the same time as the canal works.

BW have advised that they intend to commence construction works in June/July 2006 and that the 18 month construction period should mean that the works are completed by the end of 2007.

Public Open Space

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extension Leeds Liverpool Canal (RES/2)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 20 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
PH
Phil HalsallOfficer, present

All 20 on the meeting page

On this subject at Liverpool

Search all
  1. Extension Leeds Liverpool Canal (RES/2)This decision
  2. Leeds Liverpool Canal Extension - Pier HeadAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open