Resolved
Agreed that – a) That the information be noted b) Robert Corbett be requested to provide further information (when available) for 2005/06 and 2006/07 to the Committee and resident Ann O’Byrne.
Walton Neighbourhood Committee agreed this item on Wednesday 7 June 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – a) That the information be noted b) Robert Corbett be requested to provide further information (when available) for 2005/06 and 2006/07 to the Committee and resident Ann O’Byrne.
Item LIVERPOOL PARTNERSHIP GROUP 28 February 2006 Neighbourhood Renewal Fund Year 5 Report on progress in delivering the year 5 programme
Purpose of Report To update members on the progress and achievements of the NRF Year 5 (2005/06) programme for the period to December 2005.
Time scales With immediate effect
Recommendations/Actions
Partners note the contents of the report.
Background The Liverpool Partnership Group gave its approval to the year 5 NRF (05/06) programme on 24th January 2005. A condition of approval included reporting programme progress on a regular basis.
Information
£34,443,219 NRF is available to Liverpool for Year 5. In addition, to meet demand for new provision the programme had been “over programmed” to the sum of £1,362,995 giving an overall programme of £35,895,550.
Expenditure incurred by end of December 2005 was £18,872,327 some 55% of the allocation. This data has been reported to GONW in line with their reporting requirements and we anticipate full spend by the due date
Year 5 (2005/06) Outputs Achieved for the Period 1st April 05 to 30th September 05
Outputs for the period 1 April – 30 September 2005 have been collected and assessed. Verification visits are currently being undertaken. Good progress is being made by project officers in delivering key achievements against those set out in funding offer letters and it appears at this time that the majority of the outputs forecast will be achieved or over achieved by March 2006.
Outputs have been attached at annex 1, more detail on individual project outputs can be provided on request.
Beneficiaries
The number of people accessing services supported by NRF has been collected for the six month period. Verification visits are currently being undertaken to substantiate the claims made by project officers.
You will note from annex 2 that 98,842 additional people have benefited from NRF in the first six months. Annex 2 provides a breakdown of additional beneficiaries for the period 1 April – 30 September 2005 in terms of gender, ethnicity, age and disability.
Next Steps A further report will be submitted on programme achievements during the full year 5 programme in the Summer after project verification visits have been undertaken.
Contact Carol Perry Officer: UK Programmes Manager, 0151 225 3671
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NEIGHBOURHOOD RENEWAL FUND YEAR 5Report | 2 pages | DownloadRead as text |
PDF |
nrfAppendix es | 4 pages | Download |
Follow Walton Neighbourhood Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2008 | CleansingAgreed that – a) The briefing be noted b) Any specific issues regarding service provision to be reported to Geoff Jac... | Agreed | Open |
| 19 Mar 2008 | Public Question TimeAgreed that the response be noted. 2. M.S., A Residents Association “As chairman of Rice Lane and surrounding Areas R... | Agreed | Open |
| 19 Mar 2008 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 6 th February, 2008, be approved, with the following matter arisi... | Agreed | Open |
| 19 Mar 2008 | Neighbourhood Management ServicesAgreed that the report be noted. | Agreed | Open |
| 19 Mar 2008 | Neighbourhood Policing UpdateAgreed that the reports be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.