Resolved
Agreed that the contents of the update be noted and.the proposed traffic calming measures be supported
Garston Neighbourhood Committee agreed this item on Thursday 10 August 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the contents of the update be noted and.the proposed traffic calming measures be supported
BRIEFING NOTE FROM LIVERPOOL LAND DEVELOPMENT COMPANY
NEW SPEKE DISTRICT CENTRE
Introduction
LLDC reported to the Garston Neighbourhood Committee in March that enabling works had commenced on the long awaited New District Centre providing much needed retail facilities for the Speke Estate and the South Liverpool area.
The enabling works comprised a temporary access road from the Boulevard to accommodate the removal of the spoil from the former park together with site preparation works that will enable commencement of the main development/construction works. These works together with the removal of some 93,000 cubic meters of spoil was completed by the end of June with minimal disruption either within the Estate or to traffic flow on the Boulevard.
Construction Programme Status
LLDC are pleased to confirm following the appointment of Kier North west the main construction contract commenced on 3rd July 2006 which is envisaged will have a duration of approx 50 weeks and the new retail facility scheduled to open summer 2007.
The first two blocks of vacant flats are now in the ownership/possession of the developer and have been incorporated within the development site. These flats are due for demolition in August pending the disconnection of redundant services by the Statutory Utilities.
Road Closures
The Road Closures Order came into effect on 24th April 2006 with the first phase of road closures commenced on 5th July with Eastham Green and parts of Tarbock Road and Clough Road.
The Developers are implementing closures on a phased basis again in order to keep inconvenience to a minimum although due to the nature and size of the project disruption is inevitable. The remainder of the roads will be closed as and when the remainder of the SLH flats required for the development are vacated and transferred to the Developer.
The Road Closure Order will also include North Parade the physical closure of which will be phased to coincide with completion of the works to put South Parade to two way traffic. Again, prior to any road closures taking place details will be communicated to all concerned.
Land Assembly Whilst a majority of the land required for the proposed scheme is either already in the ownership of the City Council or is being acquired under existing agreements due to the nature and scale of the scheme it will be necessary to promote a Compulsory Purchase Order (CPO) in order to ensure delivery and completion of the project. In January 2006 the Executive Board of the City Council made a resolution for CPO with the CPO made on 14th April 2006 and the CPO Notices served on the affected parties.
Four objections to the CPO were received and as such the Planning Inspectorate has set a date for a Public Inquiry for three days commencing 10th October 2006. However, in the meantime should the objections be removed by negotiation then the Inquiry will not be required and the CPO confirmed accordingly.
SLH are continuing to make significant progress with the decant process on the four remaining blocks of flats at Northern Road and Penketh Green even though there is not a ready supply of appropriate alternative accommodation.
BEP/Catalyst the Head Leasee of the existing District Centre has assigned its interest to Wm Morrison Supermarkets Plc pending the transfer of title to the land on which the new development is to be constructed when Morrison will surrender the Lease/Leases to the City Council.
Remodeled Neighbourhood Centre
LLDC are continuing with the masterplanning to remodel the remainder of the existing District Centre not required for provision of the sports pitches to a Neighbourhood Centre to serve the southern part of the Estate.
LLDC are in the process off appointing consultants to draw up a provisional scheme for consultation purposes prior to implementation of the works.
Communications Strategy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New Speke District Centre: Progress ReportReport | 2 pages | DownloadRead as text |
Follow Garston Neighbourhood Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Apr 2008 | Minutes of the Last MeetingAgreed that - a) It be noted that a report following consideration of Minute 44 (Programme for a Clean Neighbourhood ... | Agreed | Open |
| 24 Apr 2008 | Spotlight Topic - Parks and Open SpacesAgreed that – a) Derek Dottie be thanked for the detailed information and assessment of performance which was present... | Agreed | Open |
| 24 Apr 2008 | Garston Regeneration – The Next Phase (NH/24)Resolved that the recommendation as amended in respect of paragraph (ii) above be approved subject to the deletion of... | Approved | Open |
| 24 Apr 2008 | Emissions at Garston DocksAgreed that the information be noted and all parties be thanked for their frank and honest contributions to the discu... | Agreed | Open |
| 24 Apr 2008 | Neighbourhood Manager's ReportAgreed that – a) The contents of the report and the update in relation to Garston Urban Village Hall, be noted; and b... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.