Resolved
Agreed that the proposals outlined be approved.
Walton Neighbourhood Committee agreed this item on Wednesday 13 September 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the proposals outlined be approved.
1.1The purpose of this report is to inform members of the Neighbourhood Committee of the need for, and to seek support for, the implementation of traffic calming measures and an associated 20mph speed limit Traffic Regulation Order (TRO) within Hale Road and Selwyn Street, Liverpool L4.
2.1As part of the 2006/2007 Safer Routes to School Programme, it is proposed to introduce traffic calming measures and an associated 20mph zone throughout Hale Road and Selwyn Street, as shown on the attached plan No 802069/1200/01 located at the end of this report. These works form phase 2 of the scheme (detailed design to construction), with phase 1 being undertaken in 2005/2006 (preliminary design to consultation).
2.2Within Hale Road there are 2 school sites. On the north side is St Francis de Sales Infant School, and on the south side St Francis de Sales Junior school. The infant school currently uses three entrance/exits from the school site at school start/finish times. The finishing time for the infant school is 15:00 hrs. The Junior school site also uses two entrance/exits from the school site, however the finishing time for the junior school is 15:30 hrs. Hale Road and Selwyn Street are residential roads, approximately 8.3metres wide, consisting of a 4.7metre running lane. With no off street parking facilities for residents to utilize, kerbside parking demand is high and because of this, visibility for pedestrians wishing to cross Hale Road in the vicinity is poor. The area also falls within the Football Match Parking Zone Area 20 and both resident parking and unrestricted parking bays (1.8 metres wide) are located within Hale Road and Selwyn Street on both sides of the carriageway, as well as no waiting at any time junction protection restrictions and school keep clear markings in the vicinity of the school sites. .
2.3This scheme has been developed as a result of St Francis de Sales Infant and Junior schools having worked on and produced School Travel Plans. These plans identify the ways in which schools will tackle problems associated with pupils travelling to and from the school site by encouraging measures such as walking, and considerate car use.
2.4As part of the School Travel Plan, the schools have identified highway improvement works which would help them achieve the aims of the School Travel Plan by improving conditions for pedestrians.
3.0PROPOSALS
3.1In order to reduce vehicle speed and ‘rat-running’ within the Hale Road and Selwyn Street area, and to improve the crossing area between the infant school and junior school sites, it is proposed to introduce eight 75mm high, 10.25m long road humps, as well as one 75mm high, 10.25m long kerb to kerb road hump (to be utilized by the school crossing patrol in assisting children to safely cross the carriageway) and one 75mm high, 4.7m long road hump. The locations for which the humps are proposed, are listed in the schedule located in Appendix A.
3.2It is also proposed to have the existing 30mph speed limit reduced to 20mph. The area affected by this speed limit reduction has also been shown within the attached plan and the locations are listed in Schedule One which is located in Appendix B.
4.0CONSULTATIONS
4.1Consultation was undertaken as phase 1 of this scheme (together with the preliminary design) and letters were sent to residents on the 7th June 2006 requesting their opinions/comments, the results to the consultation exercises are shown below;
Of the 130 letters / questionnaires sent out to residents, 49 (37.7%) were returned, of which 47 (96%) were in favour of the proposals, 1 (2%) was against and 1 (2%) did not express an opinion either way.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Proposed Traffic Calming Scheme and 20mph zone (Traffic Regulation Order)Report | 5 pages | DownloadRead as text |
PDF |
pdf plan for reportReport | 1 pages | Download |
Follow Walton Neighbourhood Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Mar 2008 | CleansingAgreed that – a) The briefing be noted b) Any specific issues regarding service provision to be reported to Geoff Jac... | Agreed | Open |
| 19 Mar 2008 | Public Question TimeAgreed that the response be noted. 2. M.S., A Residents Association “As chairman of Rice Lane and surrounding Areas R... | Agreed | Open |
| 19 Mar 2008 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 6 th February, 2008, be approved, with the following matter arisi... | Agreed | Open |
| 19 Mar 2008 | Neighbourhood Management ServicesAgreed that the report be noted. | Agreed | Open |
| 19 Mar 2008 | Neighbourhood Policing UpdateAgreed that the reports be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.