Resolved that – (i) the recommendation be approved; and (ii) the Interim Executive Director (Regeneration) be requested to submit a further report on the funding provided for the scheme by Everton Football Club and the comments made by Ward Councillors as a result of the consultation exercise. CHS/18
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
ANFIELD, CLUBMOOR, COUNTY, EVERTON, KIRKDALE, TUEBROOK AND STONEYCROFT WARDS STATUS – PUBLIC (R&T/33)
Portfolio: Regeneration and Transport Executive Member/Interim Executive Director: Councillor Keith Turner Ben Dolan – Interim Executive Director
Date of submission: Subject: Football Match Parking Zone revised programme
Report No./Background papers: Contact Officer: Ian Wiggins – 233 2712
Executive summary: To inform the Executive Board of and to seek approval for, the proposed revised programme for the future implementation of the Football Match Parking Zone (FMPZ) and to inform Ward Councillors, Neighbourhood Committees and the local community of the proposed timetable.
FMPZ Progress: Presently, the implementation of the FMPZ, in terms of the programme that was agreed in October 2003, is behind schedule. It has been determined that this has occurred for a number of reasons such as the additional time that it is taking to introduce areas as a result of further, yet necessary, consultation exercises. It is also as a result of dealing with formal objections and the subsequent changes to the scheme design that this has brought about.
It has also been found that construction costs have increased at a rate greater than anticipated, such as electrical connections for illuminated signage and the international rise in steel costs affecting signage installation costs.
These further works and additional costs have put pressure on the Highways Capital Programme, which funds the FMPZ works. The original FMPZ programme was based on there being a set level of funding available each year with each area costing a certain amount to deliver. The knock-on effect of the above further work and increase in costs is that there have not been sufficient funds to deliver the agreed programme.
Progress to date for the FMPZ is shown on attached plan no. 2020/FMPZ/06.
Recent Consultations: A consultation exercise was undertaken in Areas 6, 7 & 13 in January of this year. The response rates from Areas 6 & 7 were extremely low (5.3% and 13% respectively) and feedback from the areas indicated that there was no overall majority support for the scheme to be introduced in these areas at the present time. Furthermore, it is likely that most of the housing estate contained in Area 6 will be re-modelled in the near future as part of the Anfield Area, Housing Market Renewal Initiative (HMRI) scheme and any work undertaken at this point in time would prove to be abortive.
It is proposed therefore, that the introduction of the FMPZ in Areas 6 & 7 is not progressed at the present time. Ward Members have been advised of this together with residents and businesses.
Area 13 received a response rate of 15%, which is the threshold that is generally aimed for during consultation exercises. The majority of the responses received were in favour of the proposals and certain amendments to the scheme have been made to take into account comments that were received back as part of the consultation process.
Should the Executive Board support the revised programme then a further consultation exercise will be undertaken in Area 13 in due course to advise the community of the amended proposals and to seek their support. It is anticipated that this particular scheme can be fully implemented in the 2006/2007 financial year.
Proposed 2006/2007 Programme: At the meeting on 2 June 2006 the Executive Board approved an allocation of £150,000 from the 2006/07 Highways Capital Programme for Football Match Parking, for the continuation of the FMPZ scheme. The funding is proposed to be split as follows:- • Areas 6 & 7 - £1,500 This is to cover the costs of the letter drops that have recently been undertaken to advise residents that these areas will be now not delivered.
• Area 13 - £49,000 This is the expected cost for the design and implementation of the whole area.
• Area 14 – £94,000 This is the expected cost for the design and implementation of the whole area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.