Resolved
Resolved (6 Members voting in favour and 4 against) that the recommendation, as amended, be approved.
Planning Committee 2010/21 old approved this item on Tuesday 21 November 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved (6 Members voting in favour and 4 against) that the recommendation, as amended, be approved.
- Item 9
Ward: Riverside Site: North west corner of Kings Waterfront Development Site, Liverpool, L1
Proposal: To erect 5 no. 6kw 'quiet revolution' wind turbines
Applicant: Liverpool City Council Regeneration
Application No: 06DC/2730 Date Valid: 11th September 2006
D. C. Team: City Centre
Recommendation Approve with Conditions _______________________________________________________________
Case Officer Report
Site Description
The application site forms part of the Kings Dock Development sited along the River Mersey, now known as Kings Waterfront. The Masterplan extends over the entire former car park extending from Dukes Dock in the north to the Customs and Excise building in the south. The eastern limit of the site is bounded by Wapping Dock, while the River Mersey itself provides the western boundary.
The application site consists of just a small portion of land within the full part of the Kings Waterfront masterplan (04F/2574) approved in 2004.
The full part of the original application has been under construction for over 18 months with the steal-work of the conference centre and arena now at full height and the car park complete.
The site is outside of the Albert Dock Conservation Area and the World Heritage Site, but is within 150m of the Grade I listed Albert Dock complex.
The Proposal
The proposal has been the subject of extensive pre-application discussions with Planning Officers and consists of the erection of five 20m high horizontal axis, three-blade wind turbines. Item 9 Cont The turbines are to be arranged in a line along the north western side of the arena/conference centre. The line of turbines is in a slightly curved formation fanning out from to the buildings (continuing the concentric lines of the landscaping around the civic facilities). The turbines will be sited level with the promenade with the 1.5m raised building plinth behind.
Relevant Site History
04O/2574:
A hybrid application, full details submitted 08 March 2004 for the erection of a mixed use development, including multi-use arena, conference centre, exhibition area, public piazza with pavilion and multi-use car park; with ground floor retail space (within use Class A1), bars and restaurants (Class A3), 96 dwellings (Class C3), 2 no. electricity substations, pedestrian bridge, riverfront walkway and associated highway works; together with outline proposals for residential use (Class C3) for up to 1704 units, two hotels with ground floor retail use (Class A1), bars and restaurants (Class A3), public open space and commercial offices (Classes A2, B1), shops, bars and restaurants, community facilities; and associated servicing, highway works and landscaping. Conditional Consent – S106 Legal Agreements.
Subsequent full applications for the two hotels, three residential towers (parcel 1), substations and bridges have also been submitted and approved following application 04O/2574.
Consultations
875 letters dated 13 September 2006 were delivered to surrounding owners and occupiers in:
Armstrong Quay, Burton Close, Coburg Wharf, Grayson Street, Kings Dock Street, Mariners Wharf, Sefton Street, Stanhope Street, Hanover Street, Granary Way, Mariners Way, Sparling Street, The Anchorage, Cornhill, Park Lane, Albert Dock, Jamaica Street, Caryl Street, Parliament Street, Bridgewater Street, Queens Dock, Dwerryhouse Street, Simpson Street, Cleveland Square, Blundell Street, Tabley Street, St. James Street, Shaws Alley, Wapping Quay (North, South, East and West Quay), Worthington Street, Chaloner Street, Jordan Street, Hurst Street, Brick Street, Norfolk Street, Kitchen Street, Greenland Street, Pier Head, Castle Street, Hill Street, Derby Square, Paradise Street, South Ferry Quay, Royal Quay and various other addresses across Merseyside and beyond (in connection to representations that were received in connection with the masterplan. Item 9 Cont Site Notices were posted in the vicinity of the application site dated 18 September 2006.
Consultation responses
English Heritage
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
North West corner Kings Waterfront Development site, Liverpool 1(Riverside Ward)Report | 13 pages | DownloadRead as text |
PDF |
kings dock wind turbinesReport | 1 pages | Download |
Follow Planning Committee 2010/21 old at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 2 June 2020 be approved. | Approved | Open |
| 2 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 26 May 2020 be approved. | Approved | Open |
| 26 May 2020 | Minutes of the Last Virtual MeetingsResolved that the minutes of the Virtual Meetings of 5 and 12 May 2020 be approved. | Approved | Open |
| 31 Mar 2020 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 10 March 2020 be approved. | Agreed | Open |
| 10 Mar 2020 | Minutes of the Last Meeting 18 February 2020Resolved that the minutes of the last meeting held on 18 February 2020 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.