Children's Services Select Committee 2006/07 agreed this item on Thursday 23 November 2006. Below is the council's own wording, with the papers it was decided on.
Agreed that the Children’s Services Select Committee note that the Portfolio is forecasting an overspend of £2.4m on its approved (net) revenue budget of £365.1m. Officers are currently reviewing all options to reduce the magnitude of the forecast overspend.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Reporting officer: Stuart Smith, Executive Director (Children’s Services) and Robert Corbett, AED (Financial Management)
Contact officer: Kevin Williams, Head of Finance (Tel: 225 2114) email: [email protected]
Ward: CITY WIDE
1. Purpose and recommendations
To advise on the current (as at 30 October 2006) financial forecast for Children’s Services relating to the financial year 2006/2007.
That members of Children’s Services Select Committee be advised that the Portfolio is forecasting an overspend of £2.4m on its approved (net) revenue budget of £365.1m. Officers are currently reviewing all options to reduce the magnitude of the forecast overspend.
2. Relevant background information
This report anticipates that overall spending within Children’s Services Portfolio may exceed the allocated revenue budget by £2.4m (i.e. +0.7%). As £251.5m of the budget is funded by a ringfenced Government grant, Dedicated School Grant (DSG), officers are limited to finding offsetting saving within the remaining £113.6m non-DSG budget. Although the structure of accounts does not reflect the split between DSG and non-DSG activities a broad estimate, based on a number of assumptions, suggests that a small saving of £0.118m is forecast on the DSG services. This can only be used on DSG initiatives or carried forward for future years DSG spend. Officers are reviewing service expenditure budgets and estimated future year commitments, (particularly the demand for Non Local Authority Placements), in an attempt to identify any potential resources to fund anticipated net overspends in 2006/2007 and beyond.
This financial forecast is based upon information up to 30 October 2006. This report sets out issues that will need to be addressed during the remainder of the financial year in order to reduce the magnitude of the forecast overspend and outlines the reasons for the material variances highlighted in Annexe A.
3. Key issues
1. In 2006/2007 the Government introduced a new specific ring fenced grant, Dedicated School Grant (DSG), to fund pupil related expenditure (delegated and some centrally retained provision on behalf of schools). The DSG (£251.5m) can not be used to fund non-DSG eligible spend and therefore in 2006/2007 officers have less flexibility to move funds around. Finance staff are currently reviewing the current monitoring systems to enable future financial monitors to readily show the split of services between DSG and non-DSG funded activities.
2. At the end of 2005/2006 officers successfully requested the creation of a £29k earmarked reserve from a planned underspend on the Gladstone House budget. Permission is being sought through the Authority’s quarter two financial review report to draw down this reserve in order to part fund the refurbishment of young people’s bedrooms in the Gladstone House Norris unit. This report assumes that this request will be successful.
3. The Portfolio’s budget relies upon the achievement of c£19m of fees and charges, of which c£14m comes from the service level agreements between the Portfolio and schools for services such as meals, ICT, payroll, insurance and finance support. Half way through the year the Portfolio has successfully billed or collected 50% of this targeted income and is forecast to achieve its budget income yield.
4. The 2006/2007 budget approved in March 2006 relied upon the achievement of a number of saving options Annexe B outlines those budget proposals and provides guidance as to whether they are in line to be achieved this year. Although some of the options have been identified as not achievable, the Portfolio has been able to compensate for this from savings elsewhere within the overall budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children's Services Select Committee 2006/07 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.