Resolved that – (i) the existing Contract Sum be uplifted from £4,987,988 up to a maximum figure of £5,450,000 (an increase of £462,012) to cover the increased costs associated with the construction work; (ii) an additional contingency figure of £650,000 be provided to cover the potential costs associated with the Contractors claim; (iii) the City Councils Capital Programme be adjusted to reflect the total expenditure on this project for a sum up to £6,650,987 phased over financial years 2003/04 to 2007/08 as set out in this report; and (iv) authority be granted for the earmarked reserve to be drawn down. RES/49
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Members are aware that at its meeting on 28 May 2004 the Executive Board approved report DE/026/04 which outlined the position in relation to the delivery of the Priority 1 Project at Alsop High School. In addition, Members are also aware that at its meeting 22 December 2004 the Executive Board approved report DE/070/04 which outlined the revised principles of the BLF for PE and Sports Initiative in relation to the allocation of £9.2m made to the City Council. Furthermore; at its meeting 18 March 2005 the Executive Board approved report DE/12/05 which detailed the tenders and financing arrangements for the Alsop Community Sports centre scheme.
The following report elaborates on these principles and indicates the current position in relation to the delivery of Alsop scheme which is contained within the City Council’s BLF PE and Sport Portfolio and forms part of the City Council’s approved capital programme
The current contract value is £4,987,988 and the current approved total project costs are £5,538,975. Construction work commenced in May 2005 with a completion date of August 2006 however; the construction costs has now increased and completion of the project is now estimated to be in January 2007.
The principal reasons for the increased costs and subsequent delays are set out as follows:-
(i) significant refinements to the original design in order to fully meet the recommendations of English Heritage; (ii) significant amendments to the design of incoming statutory services especially in relation to the requirement for a new sub-station which did not form part of the original scheme; (iii) subsequent unrealised value engineering savings.
Due to the increased costs detailed above, the original contract value has increased from £4,987,988 to £5,450,000, an increase of £462,012.
It should be noted that the actual final cost of the scheme to the City Council will not be determined until such time as the Contractors claim for the subsequent disruption, delays and extension of time has been resolved. The City Council may be required to bear additional costs of approximately £650,000. Negotiation will continue with the Contractor on these issues until they are resolved however; this may be referred to adjudication if agreement cannot be reached. The proposed amended Capital Programme will include sufficient provision for this scheme to accommodate the highest potential scheme cost. The net position is a potential increase in the overall scheme of £1,112,012.
It is not possible to claim additional Big Lottery Fund grant to finance all / part of the overspend therefore; it will have to be financed by City Council general capital/revenue resources.
The existing project costs and funding arrangements are set out below.
Total Project Costs February 2005 Demolition Works (to existing building) £80,987 New Construction Works £4,987,988 Professional Fees and Disbursements £420,000 Equipment £50,000 ---------------- Total Project Cost £5,538,975
Alsop Capital Funding February 2005
BLF Grant: £4,636,975 Leisure Services revenue savings £102,000 Seed Challenge Fund £200,000 Children’s Services Capital £600,000 ---------------- Total Project Cost £5,538,975
The revised project costs and funding arrangements are set out below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.