Resolved
Resolved that the recommendation be approved. NH/34
Executive Board approved this item on Friday 2 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved. NH/34
1. The Chinese Arch in Nelson Street was provided as part of the Ropewalks Partnership works. It is believed to be one of the largest and most impressive of its type in Europe and is a major feature of the City Centre. It is now approximately 10 years old and the abrasive maritime environment combined with normal wear and tear has resulted in the paintwork becoming very hard worn and faded.
2. In May 2006 Liverpool 2020 were requested to carry out a detailed survey of the structure and to report on the likely cost of remedial works. Their resulting observations were to the effect that the structure was sound but that the paintwork was heavily weathered.
3. It was recognized at the outset that the redecoration would be complex and require a specialist contractor to deal with the situation successfully.
4. Conservation Technologies Limited the commercial arm of the Conservation Centre [National Museums Liverpool] were identified as being able to undertake the work. The alternative was to engage at potentially far greater cost and organisational difficulty specialists from China. Contract Standing Order 6.6(1) (a) and (b) will apply.
5. The overall cost of the redecoration has been identified as £86,000. The resources for the project have been identified within an approved Regeneration revenue budget. However, the works are considered to be of a capital nature, therefore the resources will need to be transferred to the Capital programme. 6. The delivery of the repair has been delayed for a number of reasons. Firstly, it is not desirable to undertake this type of work in the winter as the low temperature has a detrimental effect on the paint application and secondly there was no desire to blight the Chinese New Year festivities with the arch being shrouded in scaffolding.
7. It is presently planned to begin the work in March 07, weather permitting, and it is anticipated that the project will take between 8 and 12 weeks to complete.
8. The Regeneration Capital programme will need to be amended to include the scheme at a total cost of £86,000, the sum of £66,000 in 2006/07 and £20,000 in 2007/08.
Executive Member/Director recommendation (Councillor Keith Turner / Phil Halsall)
That –
1. Members confirm the appointment of Conservation Technologies Limited as the Contractor using contract standing order 6.5; 2. The Regeneration Capital Programme is amended to include the scheme in 2006/07 (£66k) and 2007/08 (£20k) financed from a CERA from an approved Regeneration revenue budget; and 3. Commit the expenditure.
Key Decision: No
Forward Plan Not applicable
Implementation effective from: 9 March 2007
Timescale for action: As soon as the funding is included in the capital programme, funding can be drawn down and made available when the project commences.
Reason(s) for Recommendation: Approving the proposals will ensure that a prominent and culturally important asset of the City will be displayed to its best advantage during the City Birthday year of 2007 and the Capital of Culture celebrations of 2008.
Alternative options considered: There are no alternatives. If this work does not proceed the Chinese Arch will further deteriorate with the risk of it ultimately becoming dangerous.
Consultation: Regeneration Finance Officers.
Consultation with Ward Councillors and outcome: The ward councillors have been consulted and Councillor Brant is supportive of the proposal. Further comments will be reported.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Chinese Arch (RES/66)Report | 4 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.