Resolved that – (i) authority be granted for the Council to work with the Islington Regeneration Company Ltd (IRC Ltd) to refine the Masterplan; and (ii) Officers be authorised to open negotiations with IRC Ltd to identify the possibility of joint venture regeneration in the Islington Quarter and to report back on Heads of Terms to the Executive Board which will take the final decision on the principle and detail of any future development agreement. SI/8
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This report describes progress made in discussions with the Islington Regeneration Company (IRC) by Liverpool Vision and Officers of the Council aimed at regenerating the Islington Quarter shown edged black on the attached drawing. Islington Regeneration Company is a private company limited by shares incorporated in August 2004. The constituent members of IRC and its shareholders are: Downing Developments, Pencare Developments, [name removed] and [name removed]. The company has been formed to carry out the business of property development.
This report also requests authority for officers to negotiate a Development Agreement with IRC and report back to the Executive Board with detailed Heads of Terms.
Background
2.1At its meeting on 4th July 2005 the Executive Board authorised that discussions continue with IRC with the aim of producing a policy framework for the area. It also agreed that the City Centre Member Working Group assume the role of the Member Steering Group for the project.
2.2On 15th December 2006 the Executive Board received the draft Islington Planning Framework which had been produced by GVA Grimley and Matthews & Goodman (consultants to IRC) following extensive discussions with Liverpool Vision, the City Council Planning and Building Control Services and property owners and companies trading within the area.
2.3The Board resolved that the Planning Framework be approved for public consultation purposes and be given appropriate consideration in determining planning applications. A further report is to be submitted outlining the results of the consultation process.
2.4The IRC and its various consultants have also been working up a Masterplan which builds on the Planning Framework. A draft has recently been submitted by IRC and it contains their proposals on how the regeneration of Islington should take place in 7 distinct phases of new development. The existing buildings facing London Road are largely left untouched with two properties programmed for refurbishment whilst virtually all buildings on Stafford Street are earmarked for refurbishment.
The future use is a combination of commercial, retail, residential and multi storey car parking.
2.5Whilst the draft Masterplan shows promise it will require further work by officers of Liverpool Vision and the Council (taking into account the results of the Planning Framework consultation) before it can be presented to the Member Working Group.
2.6The City Council has large areas of freehold ownership in the area but most of this is subject to long leases and there is therefore very little opportunity where the Council could provide vacant possession. IRC have over the last 18 months bought leasehold interests by agreement at a total cost of approximately £10 million. They propose to merge their interests with the Council and thus create development opportunities. IRC have also undertaken discussions with businesses in the area to ascertain their decant requirements. These discussions have covered the businesses future property requirements and whether or not they wish to stay within the Islington Quarter.
3. Proposed Way Forward
3.1Officers of the Council and Liverpool Vision to continue discussions with IRC to refine the draft Masterplan to a point where it can be presented to the City Centre Member Working Group. Central Ward Members to be consulted on the results of these discussions and their comments made known to the Member Working Group.
3.2Once the Masterplan is refined, heads of terms can be provisionally discussed with IRC covering the redevelopment of the early phases. These terms will be presented to the Executive Board for its consideration/ approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.