Liverpool City Council
Executive Board, Friday 27 April 2007

Former J&C Moores Building (R&T/67)

Approved Executive 2 papers

Executive Board approved this item on Friday 27 April 2007. Below is the council's own wording, with the papers it was decided on.

Item217e

Resolved

Resolved that the recommendation be approved subject to the words “by covenant” being inserted before the words “being restricted” in paragraph ( i ), bullet point 4.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 9 pages

Executive summary

1. Purpose

This report has been prepared by the Liverpool Land Development Company (LLDC) with assistance from the Major Projects Team at the City Council. It is requesting Members approval to accept a surrender of the existing lease of the former J&C Moores Building in Edge Lane and to grant a new lease to the Northwest Development Agency (NWDA). It also proposes the appropriation of part of the site in order to extinguish a right of way.

Background

2.1The former J&C Moores building occupies a prominent position fronting onto the southern side of Edge Lane in Liverpool. It comprises a 1930’s art deco industrial building essentially comprising two separate wings (east and west), with a central link block, and additional plant and outbuildings located to the southern end of the site. A surfaced access road runs north/south down the western end of the site, serving the subject property, and also Braithwaite’s Business Estate (Braithwaites) to the rear. Adjacent to this roadway is a narrow surfaced car parking area previously used by J&C Moores (Littlewoods).

2.2Liverpool City Council owns the freehold of the whole site, whilst the NWDA has a 999 year lease from 1938 on the main buildings. The City Council has possession of the roadway and parking area, with both the NWDA and Braithwaites having right of way across the road. 2.3. LLDC have facilitated a developer competition on behalf of the NWDA and LCC, and have selected Urban Splash Limited (Urban Splash) as the preferred developer.

2.4It is the intention that Liverpool City Council will accept a surrender of the existing lease of the main buildings and will then grant a new lease to NWDA to include the car park and roadway. NWDA will then grant an under lease of the same area to Urban Splash. This will include an obligation on Urban Splash to landscape the car park area and incorporate it into the overall re-development scheme.

2.5The current lease of the main buildings is subject to a restrictive covenant preventing the sale of alcohol from the site, and Urban Splash require this restriction to be omitted from the proposed new lease.

3. Proposed Development

3.1Urban Splash has been selected as preferred developer for the subject site. They have prepared a Preliminary Scheme for the site which sets out the proposals for the mix of uses for the site. The scheme proposals are concentrated in a three phased development with the first phase being the redevelopment of the existing west wing tower, creation of new residential spaces and retention of the clock tower to create a sky tower for a variety of functions.

3.2The second and third phases of the development will consist of a series of new build mixed use elements combining hotel, residential and business incubator uses with speciality retail.

3.3More specifically, the elements proposed are:

West Wing

 257 apartments over 3 storeys  Speciality retail to the ground floor  Underground / undercroft car parking  Commercial / business starter units

East Wing (North)

 100 bedroom hotel  Ground floor speciality retail  Commercial space  Underground / undercroft car parking East Wing (South)

 Commercial space  Underground / undercroft parking

3.4These are broad proposals, and could change slightly during the overall development process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Former J&C Moores Building (R&T/67)Report 9 pages DownloadRead as text
PDF
R&T.67 Former J&C Moores Building mapPlan 1 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Former J&C Moores Building (R&T/67)This decision
  2. Land adjoining Former J&C Moores Building, Edge Lane (REG/25)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies