Resolved
Agreed that information on an Innovative Green Energy Project – Sheltered Accommodation at Alderwood Lodge be noted.
Sustainable Environment Select Committee 2007/08 agreed this item on Thursday 28 June 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that information on an Innovative Green Energy Project – Sheltered Accommodation at Alderwood Lodge be noted.
In 2004 the Housing Repair Service undertook two pilot Solar Energy projects to assess the effectiveness of utilising solar power to augment the supply of domestic hot water to individual dwellings. Two projects were selected and two different solutions were adopted. The first project in Queens Drive utilised a tube solar panel system and the second project at Mather Avenue utilised a flat panel system.
The installations were monitored during 2004 and 2005 and the utility bills were scrutinised, where available, to assess the effectiveness of the installations. It has been assessed that during the summer months in the region of 45% of the hot water needs were provided by the panel, however, this reduced to 25% during the winter period. Manufacturers claim that up to 75% of domestic hot water can be provided by solar power.
The electricity and gas bills were assessed at the Queens Drive address and over the two year period savings of £85 on electricity bills and £34 on gas bills were identified. The hot water provided by the solar panel has a positive effect on the background central heating with the hot water thermostat cutting out earlier on the central heating boiler thus reducing total gas consumption.
The energy component source for the solar panel is derived from solar radiation consisting of direct and diffused light, thus deriving benefit from either a sunny or cloudy day.
Page 1 The average energy output per year, per panel is approximately 3500KWh. Calculating electricity at 4.3 pence per unit would provide an average energy saving in the region of £150 per annum per panel.
The cost of installing a single panel is in the region of £2,000 therefore the payback period would be a little over 13 year at current prices. However with energy prices increasing this period could reduce to less than 10 year.
The panels in these pilot studies were installed at no cost to the Authority
Looking at the aesthetics of each panel it is felt that the flat panel is visually the most attractive than the tubular panel.
The manufacturers claim that there is a saving of approximately 1 tonne of carbon emission being released into the atmosphere per year, from the introduction of each solar panel.
Proposal
The two pilot studies were undertaken on a very small scale and it was felt that a larger scale pilot study could benefit the Authority both in terms of cost saving but also promoting greener energy usage.
In view of the success, albeit small, of the individual solar panels it is now proposed to introduce a series of solar panels at the Alderwood Sheltered Housing Complex which will allow further assessment to be made.
After consultation with managers, in the Sheltered Housing Service, Alderwood Lodge was selected as the most appropriate project for a further pilot study, being in the main a series of bungalows. Whilst the initial pilot studies were undertaken by suppliers of solar panels at “no cost” clearly to undertake a larger scale scheme additional finance is required.
In 2005 a scheme for Alderwood Lodge was developed and a bid was made to the Energy Saving Trust for financial support. Unfortunately this bid was not approved. However, in 2006 further work was undertaken to determine the potential cost of the installation and the estimated cost of the scheme was assessed at a little under £60,000.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Briefing Note: Innovative Green Energy Project: Sheltered Accommodation: Alderwood LodgeReport | 3 pages | DownloadRead as text |
Follow Sustainable Environment Select Committee 2007/08 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Apr 2008 | Presentation - Women Fight Climate PovertyAgreed that – (a) a report be submitted to the next meeting of the Committee from the Libraries and Information Servi... | Agreed | Open |
| 17 Apr 2008 | Minutes of the Last MeetingIt was agreed that this matter be included on the agenda for the next meeting of the Committee. | Agreed | Open |
| 17 Apr 2008 | Response to Council Motion - Planting Trees by Councillor Roger JohnstonIt was agreed that the detailed response, as submitted by the Executive Member, which indicated that i n 2008/09 tree... | Agreed | Open |
| 17 Apr 2008 | Response to Council Motion - Boats on Lakes by Councillor Roger JohnstonIt was agreed that the detailed response, as submitted by the Executive Member, be noted. | Agreed | Open |
| 6 Mar 2008 | Minutes of the Last MeetingAgreed that the Minutes of the last meeting of this Select Committee held on 18 January are approved as a true record... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.