CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 28 September 2007

Burton Manor College (RES/28)

Agreed Executive 1 paper

Executive Board agreed this item on Friday 28 September 2007. Below is the council's own wording, with the papers it was decided on.

Item77a

Resolved

Resolved that – (i) Officers achieve resolution of the interests of local authorities previously involved with Burton Manor College at the earliest opportunity and report such resolution to the Executive Board; (ii) Officers negotiate an interim arrangement with University of Chester, on terms to be agreed, for 2007/08 as a prelude to formal long term partnership arrangements from the start of the 2008/09 academic year; and (iii) to facilitate such interim arrangements, and long term partnership, the council agree to invest capital expenditure of £324,000 for immediate remedial works to Burton Manor College, such expenditure to be financed through prudential borrowing.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

CITY STATUS – PUBLIC RES/28

Portfolio: Executive Member:

Resources Keith Turner Economic Development and Europe Flo Clucas

Date of submission: Subject: Burton Manor College 15th August 2007

Report No./Background papers: Contact Officer:

F & LTRM 09/07 Eric Wilkinson Tel : 225 2650

Executive Summary : Background :

1. Executive Board will be aware that ownership of Burton Manor College, an Adult Education facility located in Neston, Cheshire, rests with the council and that operation of the college is the responsibility of a board of governors. Whilst the college is largely responsible for its own budgetary affairs in recent years due to the gradual withdrawal of other public authorities involved in setting up the college it has been operating at a deficit which has been temporarily bridged by contributions from the council. Prior to 2002 the council made a contribution to the College averaging £50,000 p.a., which it was able to recover from the Learning and Skills Council. The ability to recover was withdrawn by LSG in 2002 and the contribution ceased thus exacerbating the budgetary difficulties The operating deficit for 2006/07 was £184,000 and the cumulative deficit temporarily covered by the council stands at £595,000. The residual rights of the other public authorities in respect of Burton Manor together with their liability for financial contributions is the subject of current correspondence.

Current Position

2. In June 2006 the governors and the council resolved to seek a partnership arrangement to assist in the operation of the College and advertised in the Official Journal of the European Union (OJEU) for interested parties to such an arrangement. As a result of the OJEU process University of Chester was identified as the preferred partner.

3. Negotiations with University of Chester have been ongoing since then and initial heads of terms have been agreed. Whilst there is still considerable work to be done to convert such heads of terms into legal agreements a firm basis exists to progress the partnership negotiations. 4. That basis which would be for a 30 year term may be summarised as :

• The governors, with support from the council, would provide c. £1 million capital investment in the college to undertake immediate essential works (c £324K) and other requisite improvement works (c £650k) to bring the property to best standards for such an establishment.

• University of Chester would commit both to operate the college on behalf of the governors and to utilise the facility for a mix of the college’s traditional residential /day courses and university courses appropriate to the college’s location.

• The University would make sufficient annual contributions over a 30 year term to cover repayment of principal and interest on the £1 million capital investment ; anticipated costs for life cycle maintenance to ensure the facility remains at best standard; and a budget for day to day repair and maintenance.

• No contribution to operating budget would be required from the governors / council with any deficit/surplus being the responsibility of the University.

• Existing college staff would transfer to the University under TUPE arrangements.

5. Executive Board may however be aware that there are complex historical issues concerning the operation of Burton Manor, with its establishment as a college involving a number of public authorities, i.e. Birkenhead, Wallasey, Bootle, Cheshire, Lancashire, University of Liverpool and Liverpool City Council. In the light of this background, officers felt it appropriate to seek barrister’s opinion on the manner in which any partnership, or other arrangements, for Burton Manor College could best be progressed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Burton Manor College (RES/28)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 21 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, apologies
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
CE
Councillor Colin EldridgeMember, present
MF
Councillor Marilyn FieldingMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, apologies
TH
Tony HunterOfficer, present

All 21 on the meeting page

On this subject at Liverpool

Search all
  1. Burton Manor College (RES/28)This decision
  2. Burton Manor College (F&R/11)Approved
  3. Burton ManorAgreed
  4. Burton Manor (CHS/57)Agreed
  5. Burton Manor (CHS/31)Agreed
  6. School Organisation Committee and Burton Manor College - Appointment of RepresentativesDecided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open