Agreed that – (i) the progress of risk management within the Children’s Services portfolio and the significant risks as at October 2007, be noted; and (ii) arrangements be made for a presentation on risk management tailored to the Children’s Services portfolio to be made 30 minutes before the meeting of the Select Committee on which the next update in relation to is submitted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Children's Services Select Committee 2007/08, 3 pages
Liverpool City Council
Report to: Children’s Services Select Committee
Subject: Risk Management Report No: CHS/72/07
Date: 15 November 2007
Reporting Officer: Tim Warren
Contact Officer: Andy Rigby
Ward: City wide
2. Purpose and recommendations To inform select committee of the progress of risk management within the portfolio and to report on significant risks as at October 2007. 3. Relevant background information Risks are self-assessed and recorded, at a service level, on the Performance Management Framework database, using the ALARM toolkit. This is the corporate standard, implemented by the Finance and Legal Services portfolio. A summary of the process is attached as Appendix A. The toolkit defines a risk as:
“the combination of the probability of an event and its consequences”.
The process involves four main elements: • the identification of a risk • scoring of the impact and likelihood of that risk occurring • identification of treatment measures • scoring of the residual risk
Each risk is managed by a designated officer and monitored by the Children’s Services Policy and Performance Team (PPT).
The Executive Director for Finance and Legal Services chairs a Corporate Risk Management Group, which is attended by officers from each portfolio. Meetings are arranged at the discretion of the chair.
Risks with a residual score of 8 or more are reported to Select Committee. Those scored at 12 or above are considered high risks. A quarterly risk report is presented to the portfolio Senior Management Team.
Recording of risks has improved in recent months due to the introduction in Children’s Services of Service Plan Review meetings. These are monthly meetings, held between Heads of Services and PPT, to discuss all elements of service planning, including risk management. Through the meetings, the need to revisit risk registers has been stressed. Emphasis has been placed on the need to consider risk in a broader sense. Attention has been drawn to the ALARM toolkit, which details categories of risk and criteria for judging the impact and likelihood of a risk occurring.
Managers have been encouraged to think laterally about risks: such as where risks are associated with any forthcoming inspections; risks to a service from council/portfolio restructures; risks arising from partnership working; monitoring of risks associated with projects.
4. Key issues The portfolio comprises 10 service areas for the 2007/08 reporting year. Each has their own service plan, containing their risk register. The services are:
Commissioning Corporate Parenting & Safeguarding Raising Achievement Service SEN and Disability Social Inclusion Strategic Planning and Regeneration Strategic Intelligence Team Surestart Youth and Community Service Youth Offending Services At the beginning of October 2007, Children’s Services had 46 risks identified, 6 of which are scored at the reporting level of 8 or above. The portfolio retains 2 risks which were considered to be high after treatment measures were put in place. See Appendix B.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children's Services Select Committee 2007/08 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
Sure Start / Children’s Centres UpdateIt was agreed that a briefing note be provided on the extent of service delivery and numbers assessing the centre. Ø ...
Liverpool Parenting Strategy (CHS/36)Agreed that the decision of the Executive Board be supported and the Liverpool Parenting Strategy be endorsed in so f...
Use of Sunbeds (Notice of Motion)Agreed that the terms of the Motion be supported in principle in so far as this Committee is concerned and the Execut...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.