Resolved that - (i) the proposals for additional public realm works and costs at Pier Head, Mann Island and Strand be approved; (ii) subject to receipt of revised offer letters - · accept revised grant offers as outlined in the financial implications; · amend the Capital Programme to reflect these offers; and · commit the additional expenditure at Pier Head/Mann Island public realm and Strand; (iii) all areas of the Pier Head public realm shall be maintained to the refurbished standard for a minimum of ten years from practical completion. Maintenance shall be in accordance with the Mann Island and Pier Head public realm management and maintenance protocol; and (iv) the Team Leader, City Centre Projects Team be the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises. REG/35
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Purpose To update Members on financial changes to various projects at the Pier Head including Pier Head Public realm, Pier Head acquisitions and the Strand CCMS.
Background
In July 2006 Members approved the design, procurement and delivery strategy for public realm works in association with the Liverpool Canal Link at Pier Head and the Mann Island mixed use development to the value of £6.5m funded by NWDA and ERDF. The works at Pier Head are being delivered by British Waterways as part of the Liverpool Canal Link Contract and at Mann Island by Neptune and Countryside Developments.
Since that time other regeneration projects have been brought forward at the Pier Head and the scope of the public realm works has changed to keep pace with these. Most notably the Council acquired the Shanghai Palace Chinese restaurant in late February with funding support from NWDA. ( approved by Members 1st Dec 2006, report No EDR/202/06) Since then asbestos has been removed from the building and services terminated. Complications arose with the asbestos removal with the need for some removal as part of the demolition process. This is now being undertaken by Merseytravel who are demolishing the restaurant on behalf of the Council along with the existing ferry terminal prior to commencement of the new ferry terminal. The proposals for the new ferry terminal received planning consent on 13th March and works commenced in July. The anticipated completion date for the building is October 2008. Pier head acquisitions When the acquisitions were reported to Members in December 2006 it was envisaged that this project would include for delivery of associated public realm works and figures included for this. However it has been more efficient and economic to keep all public realm investment together under the Pier Head Public Realm Works budget line and therefore the financial profiles have been amended. An application has also been made under the Pier Head acquisitions approval for increased costs in respect of the additional asbestos.
Pier Head Public Realm The funding secured for the Pier Head public realm has been enhanced by an increased external contribution from British Waterways to the sum of £ 794,270 which will allow a comprehensive delivery of public realm works up to the canal edge. The introduction of the ferry terminal has had an impact on costs necessitating additional design work and increased scope of works around the ferry terminal. In addition there have been some increased costs as a result of the late letting of the canal contract by British Waterways. The additional funding will be met by both NWDA and ERDF funding and will cover additional scope and costs.
Mann Island/Strand Improvement The Pier Head public realm project also includes for public realm works around the canal basin at Mann Island to be implemented by Neptune Developments /Countryside Properties. These works will now not be completed until 2009 and therefore it has been necessary to dissociate them from the ERDF programme. It has been agreed with funders that the works at Mann Island will now be wholly funded via NWDA. The amendments to the funding profile together with the additional costs result in an increase in NWDA contribution and no net change in the ERDF contribution on the Pier Head and Mann Island public realm project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.