Resolved
Agreed – a) The update be noted b) A meeting be arranged of this Committee during March, 2008, to review performance of NPWGs c) Members be circulated with an up to date breakdown of use of the Neighbourhood Fund
Alt Valley agreed this item on Wednesday 5 December 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed – a) The update be noted b) A meeting be arranged of this Committee during March, 2008, to review performance of NPWGs c) Members be circulated with an up to date breakdown of use of the Neighbourhood Fund
At its meeting in August, the joint committee agreed Alt Valley Neighbourhood Agreement. This covers the period between April 2007 and March 2010. The agreement links back to Liverpool’s Local Area Agreement (LAA) and provides targets for joint working under the four themes of:
- Economic Development and Enterprise - Safer, Stronger Communities - Children and Young People - Healthy Communities and Older People
The purpose of this 6 Ward meeting is to monitor and review progress of the Neighbourhood Agreement and to agree remedial actions as required.
The Neighbourhood Agreement does not set out to specify all actions to be taken over the next three years to achieve neighbourhood targets. This detail is to be defined and driven through the theme based Neighbourhood Partnership Working Groups (NPWGs). These are comprised of staff from relevant partner agencies including voluntary, community sector and councillors.
To date, two NPWGs have been established in Alt Valley – Safer, Stronger Communities and Economic Development & Enterprise. Progress in these groups is outlined below.
2. Progress
i) Safer Stronger Communities (SSC) The priorities for SSC NPWG are set out in appendix 1. To date, it has met on two occasions and a further meeting is due to take place on 29th November. It is chaired by Neighbourhood Management and has agreed terms of reference and membership.
The group receives City Safe performance monitoring and environmental enforcement information as standard items. These help to identify hotspots and plan activity. It also maintains an overview of initiatives taking place across the area such as Respect and the Targeting Gangs Action Programme. To assist the planning process, the group has requested information from partner organisations to identify the resources they can contribute to agreed priorities (funding, staffing, skills etc.). This is ongoing. In addition, a number of task and finish groups have been set up to address the specific issues detailed below:
a) Burglary Reduction The group is chaired by the Crime Reduction Manager, Community Safety. It is tasked with developing an action plan to reduce domestic burglary within particular areas of Alt Valley. The action plan is supported with £30,000 funding from City Safe. To date, £13,500 has been allocated for Smartwater property marking and Operation Loop line. It is envisaged that the balance of funding will be allocated at the next meeting on 29th November. Proposals being considered include security fencing on Daneville housing estate, introducing PIR lighting and support for police search operations
b) Proud Norris Green Alt Valley NMS has previously managed a successful ‘Pride in our Community’ programme. This operates on similar lines to the Respect Programme with partners working together to make a tangible impact within a neighbourhood over a short time period. Fazakerley, Warbreck and Croxteth have had programmes and, more recently, the Croxteth Ward was the focus for a week long Respect Action Programme. In addition, a police led mini Respect programme is planned for Fazakerley in December.
In view of the success of these programmes and the desire to roll them out to other areas of Alt Valley, the NPWG agreed to set up a task and finish group to progress a ‘Proud Norris Green’ programme. This group had an initial meeting on 26th November with the week of action being planned to start on 10th March, 2008. As with Respect, the intention will be to develop themed activities based on the various blocks within the Neighbourhood Agreement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Neighbourhood Area Agreement: Progress Report Against PrioritiesReport | 5 pages | DownloadRead as text |
Follow Alt Valley at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Mar 2008 | Minutes of the Last MeetingAgreed that – a) the minutes be approved as a correct record and; b) the key actions of the Neighbourhood Agreement b... | Agreed | Open |
| 12 Mar 2008 | Local Area Agreement (LAA) Performance Report - Alt ValleyAgreed that – a) the information provided be noted; b) Comments made be passed on to Liverpool First and any further ... | Agreed | Open |
| 12 Mar 2008 | Neighbourhood Partnership Working GroupsAgreed that – a) the minutes of the Economic Development & Enterprise NPWG be noted b) Geoff Jackson should liaise wi... | Agreed | Open |
| 5 Dec 2007 | Minutes of the Last MeetingAgreed – a) That the minutes of the last meeting be approved b) An appropriate addition be made to the key priorities... | Agreed | Open |
| 5 Dec 2007 | Secondary School ReorganisationIt was agreed that the issues raised be noted and that Councillor Marilyn Fielding raise the issues with Councillor P... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.