Resolved

Resolved that – (i) the City Council’s continued support for the Cities of the Isles network be endorsed; (ii) the Executive Director (Regeneration) be nominated as the Lead Officer for input into Cities of the Isles and that the Assistant Executive Director (Policy and Programmes) continues to co-ordinate the City’s input, and (iii) the City Council agrees to host the 2008 Summit and that a further report be submitted in March 2008 regarding the proposed arrangements for the event. NH/18
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

INTRODUCTION

1. The purpose of this report is to:

• inform Executive Members of this year’s Cities of the Isles (COTI) Conference in Dublin; • seek agreement that the Executive Director for Regeneration, via Policy and Programmes Division, will continue to lead on, and co- ordinate, Liverpool’s input to the network on behalf of the Council and its partners as relevant. • confirm agreement to the necessary resources to organise and host a Cities of the Isles summit meeting in Liverpool in October 2008.

BACKGROUND TO THE CITIES OF THE ISLES (COTI) NETWORK

2. The Cities of the Isles (COTI) Partnership is a network of six UK and Irish City Councils (Belfast, Cardiff, Dublin, Edinburgh, Glasgow and Liverpool). These cities have agreed to come together to share urban regeneration experiences, develop joint projects and establish a co- ordinated approach to issues of strategic importance. 3. All six cities face the same or similar regeneration challenges. The COTI Partnership gives all the participating cities the chance to showcase their regeneration activities, providing an opportunity for the network to explore issues of common importance. 4. The current COTI network grew out of the Irish Sea Partnership (ISP) which was established in 1998. The ISP involved Belfast, Dublin and Liverpool, three cities separated by a narrow strip of water.

5. The Irish Sea Partnership was a platform which brought these cities together annually to consider issues of mutual interest relating to regeneration and economic development. The first conference was held in 1998 and the following year Glasgow joined the partnership at the event held in Belfast.

6. In March 2000 the Chief Executives of Dublin, Belfast, Cardiff, Edinburgh and Liverpool indicated their aspiration to establish a formal grouping to shadow the agenda established by the Council of the Isles following the Good Friday Agreement. Rather than establish a parallel network it was agreed to invite the Welsh and Scottish capital cities to join the ISP which assumed the title, Cities Of The Isles (COTI).

7. The Chair of COTI is a passing responsibility held by the host City for the year leading up to a Conference. Liverpool will host the Summit in 2008 and is therefore currently Chair of COTI.

THE COTI BUSINESS PLAN 2005

8. Eddy Adams Consultants Ltd was appointed in 2005 to develop a short robust business plan.

9. The document entitled COTI: Moving Ahead – offered a range of recommendations regarding commitment to a more focussed and structured COTI network for a limited review period. Following the Cardiff COTI Conference in 2006 the Business Plan was endorsed with each City taking the lead role in a start/finish Task Group with a view to including other cities who had a national interest in that task. For a variety of reasons, mainly capacity, the Task Group approach had limited success however Cities continued to collaborate on issues of mutual concern or projects on a regular basis.

THE DUBLIN COTI SUMMIT 2007

10. The Summit took place in Dublin this year (October 11 and 12) and a delegation of 3 attended from Liverpool; the Executive Member for Corporate Services (Cllr Peter Millea), Interim AED Policy and Programmes (Mark Kitts), and the Policy/Programmes Coordinator from ‘Liverpool First’ (Andy Snell).

11. It was agreed by COTI Cities in the lead up to the event that it would be a Summit with invitations limited to a senior politician and officers and or partners. The format was a boardroom summit meeting hosted by Lord Mayor of Dublin, Cllr Paddy Burke and facilitated by Professor John Ratcliffe, founder and chairman of the ‘Futures’ academy at the Dublin Institute of Technology.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cities of the Isles Network Liverpool 2008 (EDE/18)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Cities of the Isles Network Liverpool 2008 (EDE/18)This decision
  2. Cities of the Isles Network (REG/63)Agreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open