Church Ward - Calderstones Road - Local Safety Scheme
ApprovedCommittee1 paper
Highways and Public Spaces Representation Committee 2020/21 approved this item on Monday 21 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved that 1. Having considered all of the written and oral representations, the objections be not sustained and the application be approved; 2. The Highways Manager be requested to start early consultation on the remainder of the scheme 3. The Executive Board be requested to approve capital expenditure on the remainder of the scheme.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Highways and Public Spaces Representation Committee 2020/21, 40 pages
Purpose of report
The purpose of the report is to share with the committee the feedback received from the community following the legal advertisement of the Traffic Regulation Orders for the above scheme. In addition, the report identifies a strategy to phase the works which would improve the likelihood of capitalising on funding available within the 2007/2008 financial year thereby, allowing a significant element of the scheme to be constructed within the current financial year.
Recommendation
Given the multitude and variation of the comments received from the Green Lane community, a staged approach be taken to implement the Calderstones Road and Harthill Road sections only of the scheme. This approach has the support of the Neighbourhood Committee, and as such the remaining objections relating to these sections be over-ruled. INFORMATION 1.0 Background
1.1This traffic calming scheme was identified from the Traffic Calming Priority List, which forms part of the City Council's Local Safety Schemes Programme 2007 / 2008.
1.2The Local Safety Schemes Programme was approved by the Executive Board on the 22nd June 2007. The Local Safety Schemes Programme looks to address road traffic collisions within the city in line with Government casualty reduction targets set for 2010.
1.3The traffic calming priority list focuses primarily on vulnerable road users (pedestrians and cyclists) to which traffic calming schemes have the greatest benefit.
1.4The proposed scheme involves two Traffic Regulation Orders, one for Green Lane specifically and the other covering Harthill Rd and Calderstones Rd. Both elements include road humps, a 20mph speed limit, whilst Green Lane also includes for parking restrictions.
1.5Following engagement with the community it.became increasingly clear that the residents of Green Lane experience community problems that cannot be resolved through the implementation of an accident reduction scheme. The community, through their feedback, identified different priorities and solutions for Green Lane. The issues varied, but of particular concern was the frequency of bus movements along Green Lane and the availability of parking space. With the timeframe available it would be difficult to balance the various aspirations the community have into a single all encompassing scheme.
1.6As a result of this, the matter was discussed with Church Ward Councillors and subsequently taken to the Wavertree Neighbourhood Committee on the 18th December 2007. During this meeting the committee indicated its support to take a staged approach to the scheme. This would involve the introduction of the Harthill Rd and Calderstones Road elements of the scheme, subject to dealing with objections, and further investigatory works on Green Lane.
2.0Consultations - Voluntary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Highways and Public Spaces Representation Committee 2020/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.