Resolved that the proposed list be approved as the basis for consultation and that in addition - (a) regardless of buildings being of listed status, or located within a conservation area, the validation list should also include reference to buildings or areas that might potentially generate local interest; (b) reference to Construction Management Plans should be included within the list; and (c) the Planning Manager be requested to report to a future meeting in relation to enforcement activities.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Planning Committee 2010/21 old, 22 pages
Purpose of report
The Government is amending the requirements for the validation of planning applications so it is now necessary to have a formal local list. The Planning Committee is asked to endorse the list and details set out in Appendix 2 Local requirements – Liverpool’s Validation Checklist as a basis for consultations with applicants/agents and interested bodies.
2. Validation of Planning Applications Checklist
The Government is amending the Town and Country Planning (General Development Procedure) Order 1995 (GDPO) from April 2008 to introduce a standard application form and associated guidance required.
It will be introducing a national/statutory requirement for a minimum level of information and the scope of information which should be supplied with planning applications to enable the proper validation and determination of an application. The information which the National List currently requires is quite limited and Local Government advise local planning authorities that they should produce local lists (validation checklist). At present Liverpool has a Validation Item 4
Checklist which accords with Best Practise advice. However, this needs to be updated in a formalised way, including getting the checklist agreed by Planning Committee and undertaking consultation.
The changes will impact on the format and content of standard planning application forms and intend to improve the process of receiving and processing of planning applications. The report sets out a list of local requirements in Liverpool’s Validation Checklist for various applications and as an initial stage of the process asks members to endorse the requirements as a basis for consultation.
3. The Importance of Validation on Performance
Local planning authorities are required to complete quarterly returns to ODPM (known as the PS1 and PS2 returns). These returns are used to determine their performance in line with the government’s Best Value Performance Indicator 109 a, b, c targets for each of three categories of planning applications: Major, Minor and Other. In order to ensure that this information is completed on a consistent basis the local planning authority should have a validation checklist system in place.
In order to meet the Government targets local planning authorities should aim to determine whether an application is valid within 3 to 5 working days from the date of receipt. A letter should be sent to the applicant confirming the validity of the application and confirming the start date of the statutory period for determination and the date from when an appeal can be made. Where local planning authorities consider an application to be invalid, the notification letter should include a statement of the steps and the outstanding information required from the applicant to achieve validation – this should be based upon the local planning authorities own checklists.
4. National Statutory Requirements
Applications for full planning permission are required to be accompanied by the following: Item 4
• The standard application form • The location plan • Site and other plans • Block plan of the site • Existing and proposed elevations • Existing and proposed floor plans • Existing and proposed site sections and finished floor and site levels • Roof plans • Completed Ownership Certificates • Notice(s) • Completed Agricultural Holdings Certificate • The correct fee where one is necessary • Design and Access Statements (where required)
See appendix 1 for details required for each of the above
5. Local requirements – Liverpool’s Validation Checklist
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.