Liverpool City Council
Executive Board, Friday 14 March 2008

Update on Lime Street Gateway Project (RES/50)

Agreed Executive 2 papers

Executive Board agreed this item on Friday 14 March 2008. Below is the council's own wording, with the papers it was decided on.

Item185c

Resolved

Resolved that the City Council - (i) agrees to act as accountable body for £1,203,670 grant funding from the NWDA for the acquisition of the Lime Street Gateway site; (ii) agrees that on receipt of funding agreement from the NWDA - · authority be granted for the Executive Director (Regeneration) to accept NWDA grant of £1,203,670; · the Divisional Manager Regeneration Policy and Programmes be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of the grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant; · the City Council’s capital programme for the year 2007/08 be adjusted to reflect expenditure of £1,203,607 in respect of this acquisition; and · expenditure be committed to enable the acquisition to proceed; (iii) agrees to acquire the Lime Street Gateway site in advance of the scheme proceeding, and by the end of March, 2008, to meet the NWDA and English Partnerships funding arrangements, subject to the negotiation of safeguards from English Partnerships and the NWDA which minimise any future risk to the Council; (iv) agrees to act as accountable body for additional grant funding from NWDA to enable demolition of the tower and completion of public realm works, this is subject to agreement on the level of funding involved and confirmation that this will be at nil cost to the Council. The Council shall enter into the necessary legal agreements with NWDA and English Partnerships, details to be agreed by the Executive Director for Regeneration in consultation with the Acting City Solicitor. The agreed amount will be reported to the Executive Board and authority sought to amend the capital programme for the relevant years to incorporate this additional funding; and (v) would seek the maximum dowry available from English Partnerships towards the long term maintenance and management of the new public realm, with any shortfall to be met from the Council’s budget in 2011/12 and beyond. CPS/5
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 7 pages

APPENDIX 1 CITY (L.18) STATUS - PUBLIC

Portfolio: Leader Executive Member/Director: Councillor Warren Bradley/Ben Dolan

Date of submission: 7 February 2006 Subject: Lime Street Gateway

Report No: Contact Officer: Ben Dolan 225 3414/ Alan Burke

Introduction

Lime Street station is the principal access to the City Centre for some 45,000 people on a daily basis. It is a major interchange which facilitates the movement of people between the overland rail network, the Merseyrail underground system and the bus network. At present the station entrance and its environs are a major disappointment. The predominant feeling is one of neglect and decay. The standard of the public realm is poor, as is the overall quality of the user’s experience. Movement in and around the station is not efficient. The existing Concourse House tower and retail units (many of which are currently empty) restrict pedestrian access and block important views of the station itself. A radical intervention is required to rectify the situation and deliver a new entrance gateway for the city of an international standard.

In early 2005, following a development competition managed by Liverpool Vision, English Partnerships, the predominant landowner of the site immediately fronting the station, appointed developer Iliad as its preferred private sector partner for a major re-development scheme. The scheme will deliver an extended area of new world class public realm space at the front of Lime Street Station, incorporating a new fully accessible entrance to the Station itself, and a high quality contemporary landmark building.

English Partnerships is now working jointly with Iliad and Network Rail to agree detailed implementation arrangements for the scheme. Liverpool Vision is co-ordinating the project on behalf of the public sector partners. English Partnerships is the lead public sector investor.

English Partnerships has sought the City Council’s support in facilitating the scheme as a result of the financial restrictions placed on it by new Resource Accounting regulations which have recently come into force and which have required it to reconsider the terms upon which the Development Agreement with Iliad is dealt with.

This report seeks to: • Provide the Executive Board with up-to-date information in relation to the status of the Lime Street gateway project.

• Set out the proposed arrangements for moving forward with delivery and implementation of the scheme, including the proposed role of the City Council in that respect.

• Secure approval for the City Council to become involved in facilitating the project in the way outlined, subject to the detailed recommendations contained within this report.

Project Content & Delivery

The Lime Street Gateway project will deliver a world class gateway for Liverpool City Centre by:

• providing a high quality public realm environment in the immediate environs of the station • delivering a landmark mixed use building which will create a benchmark for sustainable city centre living • enabling fully accessible access from Lime Street directly to the Station for the first time.

English Partnerships is the lead public sector partner in the initiative and has already acquired much of the site needed to deliver the scheme. In early October 2005 English Partnerships resolved to prosecute a CPO if needed, in order to secure delivery of the remaining land and property interests necessary to deliver a comprehensive scheme.

English Partnerships has secured internal funding approval to invest some £19m in the project over the next 3 years. ODPM approval to this investment was secured in late 2005. Along with investments in Kings Waterfront and in Housing Market renewal areas such as Edge Lane this investment in the Lime Street gateway represents its major contribution to regeneration in the city at the present time.

Implementation Arrangements

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
L.18: Lime Street GatewayReport 7 pages DownloadRead as text
PDF
Update on Lime Street Gateway Project (RES/50)Report 6 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Update on Lime Street Gateway Project (RES/50)This decision
  2. Lime Street Gateway (A&D/50)Approved
  3. Lime Street Gateway (A&D/16)Approved
  4. Lime Street Station, Concourse Shops, Concourse House, Lime Street, Liverpool 1(Central Ward)Approved
  5. Lime St Station and Lime Street Chambers, Lime Street, Liverpool 1(Central Ward)Approved
  6. Concourse House, Concourse shops and Gloucester Street Shops, Lime Street, Liverpool 1(Central Ward)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies