Children’s Services Capital Programme - update February 2008 (CHS/37)

Noted Executive 4 papers

Executive Board noted this item on Friday 28 March 2008. Below is the council's own wording, with the papers it was decided on.

Item194o

Resolved

Resolved that - (i) authority be granted to increase the budget by £47,462 on the Improving Schools Security Project (BEERH68) to be financed from: · New Pupil Places 2006/07 (BEESA59) - £33,000; and · New Pupil Places 2007/08 (BEESA82) - £14,462; (ii) authority be granted to increase the budget by £38,244 on the project to refurbish the roof at Anfield Infants and Junior Schools (BEESS17) to be financed from - · New Pupil Places 2007/08 (BEESA82) - £31,370; and · Surplus of Formula capital (BEEPP85) - £6,874 (iii) authority be granted to increase the budget by £2,354 on the project to replace windows at Fazakerley Primary School (BEESN69) to be financed from - · Surplus of Formula capital (BEEPP85) - £2,354; (iv) authority be granted to increase the budget by £32,000 on the project to construct a new ICT block at Alsop High School (BEEPN56) and to increase the authorised expenditure to £2,395,000 following settlement of the final account to be financed from - · Modernisation Secondary (BEERX86) - £32,000; (v) authority be granted to increase the budget by £2,626 on the project relating to the upgrading of heating systems at 11 schools (BEESB74) to be financed from - · Surplus of Formula capital (BEEPP85) - £2,626 (vi) authority be granted to the following virements in the Children’s Services Capital Programme to reflect savings achieved on completed projects: Project Budget Virement from Cost Centre Virement To Cost Centre Electrical works 2005/06 £90,000 BEERJ32 BEEPR26 Woolton Juniors – ICT /Library £25,000 BEESB88 BEEPR26 Windsor Primary – Infants remodelling £17,000 BEERS73 BEEPR26 Fazakerley Primary – Junior remodelling £6,000 BEERS36 BEEPR26 Alsop High School – Boundary Wall £29,000 BEERM45 BEEPR26 Alsop High School – Music Arts and Drama Block £41,500 BEEJE58 BEEPR26 (vii) the slippage in the Children’s Services Capital Programme as set out in Annex A of the report submitted, be noted; (viii) authority be granted to accept the capital allocations from the Department of Children, School and Families as set out in Annex B of the report submitted; and (ix) the Capital Programme be amended accordingly.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 7 pages

Executive summary

The purpose of the report is to seek authority for the amendments to the Children’s Services Capital Programme set out in the report below, accept additional central government capital allocations and advise on slippage.

Project variances

The following project variations together with reasons are identified below:

1. Improving School Security – BEERH68

To increase the budget by £47,462 to reflect increased costs in connection with the programme to improve security at a number of schools involving fencing improvements, secure bin stores, cctv and security lighting. To be financed from:

• New Pupil Places 2006/07 (BEESA59) - £33,000 • New Pupil Places 2007/08 (BEESA82) - £14,462

2. Anfield Infants and Juniors, roofing works – BEESS17

To increase the budget on the project to refurbish the roof at the infants and junior school by £38,244 as a result of the discovery and treatment of more extensive dry rot in the roof timbers. To be financed from:

• New Pupil Places 2007/08 (BEESA82) - £31,370 • Surplus of Formula capital (BEEPP85) - £6,874

3. Fazakerley Primary, window replacement – BEESN69

To increase the budget by £2,354 on the project to replace windows at the above school as a result of the requirement to remove and dispose of some asbestos panelling. To be financed from:

• Surplus of Formula capital (BEEPP85) - £2,354 4. Alsop High School, Phase 4 – BEEPN56

To increase the budget on the above project by £32,000 and the authorised expenditure to £2,395,000 following settlement of the final account. The increased costs related to an extension of time with costs given to the contractors during construction as a result of delays during the school exam time. To be financed from:

• Modernisation Secondary (BEERX86) - £32,000

5. Mechanical Woks 2006/07 – BEESB74

To increase the budget by £2,626 on the project relating to upgrading the heating systems at 11 schools following the settlement of the final accounts on all schemes. To be financed from:

• Surplus of Formula capital (BEEPP85) - £2,626

6. Electrical Works 2005/06 – BEERJ32

To reduce the budget by £90,000 on the project to carry out electrical works at 9 schools. All works are now complete and the savings have accrued as a result of unspent contingency. The savings be added back to the Modernisation budget to be available to finance other projects within the Capital Programme.

7. Woolton Juniors ICT room/Library – BEESB88

To reduce the budget by £25,000 on the project to remodel part of the junior school building to form a library/resource area and extended ICT room. The final account has been settled and the savings have accrued as a result of unspent contingency and a reduction in provisional sums. The savings be added back into the Modernisation budget to be available to finance other projects within the Capital Programme.

8. Windsor Primary School – Remodelling of infants – BEERS73

To reduce the budget by £17,000 on the project to remodel the infants wing at the school. The final account has been settled and savings have accrued as a result of unspent contingency and a reduction in provisional sums. The savings be added back into the Modernisation budget to be available to finance other projects within the Capital Programme.

9. Fazakerley Primary – remodelling of juniors – BEERS36

To reduce the budget by £6,000 on the project to remodel the junior wing at the school. The final account has been settled and the savings have accrued as a result of unspent contingency. The savings be added back into the Modernisation budget to be available to finance other project within the Capital Programme. 10 Alsop High School – Boundary Wall – BEERM45

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHS.37 cap prog ANNEXE A Feb 2008Appendix 3 pages Download
PDF
CHS.37 cap prog ANNEXE B Feb 2008Appendix 1 pages Download
PDF
CHS.37 cap prog ANNEXE C Feb 2008Appendix 1 pages Download
PDF
Children’s Services Capital Programme: update February 2008 (CHS/37)Report 7 pages DownloadRead as text

At this meeting

Whole meeting
192Minutes of the Last MeetingApproved 193Freedom of Information Act and Data Protection Act RequestsNoted 194aLiverpool Vision Update (L/8)Approved 194bArchbishop Derek Worlock and Bishop David Sheppard Statue (RES/52)Approved 194cBus Layover in the City Centre (REG/46)Agreed 194dTransportation Capital Programme Update (REG/50)Approved 194eFinancial Arrangements for Merseyside Road Safety Partnership (REG/51)Agreed 194fDraft Transport Supplementary Planning Document (REG/52)Approved 194gMerseyside Rights of Way Improvement Plan (REG/53)Approved 194h3 Year Transportation Capital Programme (REG/55)Approved 194iDisposal of land at 44-50 Sandy Lane (NHS/22)Decided 194jIntroduction of Eligible Service Charges in Homeless Hostels (NHS/23)Decided 194kGarston Regeneration – The Next Phase (NH/24)Approved 194lHousing Demolition Tenders & Expenditure Anfield Phase 1 and 2 and Edge Hill Phase 2 and 2a CPO’s and 24-36 & 56-64 Gladstone Road (NH/25)Agreed 194mDeclaration of surplus land at Otterspool Drive (E/8)Decided 194nLiverpool Parenting Strategy CHS/36)Approved
194oChildren’s Services Capital Programme - update February 2008 (CHS/37)This decision
195Major Plans and Strategies - Regeneration and Economic Development Committee - 25 February 2008Agreed 196Anfield, Tuebrook and Stoneycroft and Old Swan and Liverpool East Neighbourhood Committees Joint Youth Sub-Group – 21 February 2008Approved 197Traffic and Highways Representations Committee - 6 March 2008Noted 198Overview and Scrutiny Select Committee - 4 March 2008Noted 200aLiverpool Direct Limited (L/9)Agreed 200bRoyal Court Lease (L/10)Approved 201Exclusion of Press and PublicDecided 202aFinancial Assistance to Businesses (EDE/23)Approved 202bKensington Neighbourhood Centre (REG/49)Private

Who was there

12 of 17 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
FC
Councillor Flo Clucas OBEMember, present
CE
Councillor Colin EldridgeMember, present
MF
Councillor Marilyn FieldingMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
TH
Tony HunterOfficer, apologies
PH
Phil HalsallOfficer, present

All 17 on the meeting page

On this subject at Liverpool

Search all
  1. Children’s Services Capital Programme - update February 2008 (CHS/37)This decision
  2. Children's Services Scorecard and Performance HighlightsDecided
  3. Children's Services Cabinet Member UpdateAgreed
  4. Children's Services Cabinet Member UpdateAgreed
  5. Recruitment to post of Director of Children and Young People's ServicesApproved
  6. Arrangements for Transition from Children's Services to Adult ServicesAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies