CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Liverpool Schools Forum, Thursday 8 May 2008

Claw-back of excessive schools balances (Phase 2): Resourced Schools

Agreed Committee 1 paper

Liverpool Schools Forum agreed this item on Thursday 8 May 2008. Below is the council's own wording, with the papers it was decided on.

Item35

Resolved

Agreed that – (a) the Schools Forum support earmarking of proportionate claw-back relating to Phoenix and Springwood Heath Schools as outlined in paragraph 5 of the report submitted to the benefit of special schools provision; (b) the matter be referred to the Funding Formula Sub-Group to discuss utilisation with representatives from ALSSH; and (c) a recalculation take place without the element of outreach funding and this be advised to the next meeting.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Liverpool Schools Forum, 2 pages

Purpose of report

To respond to Liverpool Schools Forum’s request to endorse the principle of aligning claw-back to the benefit of same sector withdrawal.

RECOMMENDATION(S)

To:

(i) Earmark proportionate claw-back relating to Phoenix and Springwood Heath Schools as outlined in paragraph 5 to the benefit of special schools provision; and

(ii) Refer the matter to Funding Formula Sub-group to discuss utilisation with representatives from ALSSH.

INFORMATION

1. Liverpool Schools Forum approved paper SF08002 on 10 January 2008 to claw-back £470,668 from 20 maintained schools.

SF08023 2. The breakdown can be summarised as follows:- Sector Amount Use Primary £230,927 Hardship Fund for primary sector Secondary £239,741 BSF purposes Total £470,668

3. However, at the request of ALSSH, the Forum supported the principle that claw-back should benefit the same sector from which withdrawal was made. Hence, the proportionate elements attributed to the resourced schools should be ring-fenced to special schools sector.

4. For Phase 2 clawback, the following is now subject to proportionate realignment: Phoenix £30,359 Springwood Heath £64,759 Total £95,118

5. The respective schools budget shares are considered as an appropriate proxy for claw-back realignment purposes. This can be demonstrated as follows:-

Claw-back 07-08 % Special Proportion Amounts School Budget with AWPU of clawback deducted deemed special Phoenix £30,359 £1,374,953 37.54% £11,396 Springwood Heath £64,759 £1,460,191 37.53% £24,302 £35,698

6. It is suggested that the matter of utilisation (within the special schools sector) is referred to Funding Formula Sub-group for discussion and agreement.

7. Recognition needs to be made that actual utilisation of claw-back from Springwood Heath cannot be incurred until all outstanding PFI issues have been resolved.

8. Finally, it is also worth noting that the revised primary-related Phase 2 claw-back now stands at £195,229.

FINANCIAL IMPLICATIONS: Apart from the reduced Hardship Fund now available to the primary sector, there are no financial issues other than those identified in report SF08002.

TIMESCALE FOR ACTION: Immediate.

CONSULTATION: As discussed and agreed at Liverpool Schools Forum meeting on 10 January 2008.

BACKGROUND PAPERS: Report SF08002: Excessive Schools Balances – Phase 2 – Proposals for and use of claw-back (Liverpool Schools Forum, 10 January 2008).

SF08023

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Claw-back of excessive schools balances (Phase 2): Resourced SchoolsReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Claw-back of excessive schools balances (Phase 2): Resourced SchoolsThis decision
  2. Reimbursement of Phase 1 claw-back moneyAgreed
  3. Excessive Schools Balances: Phase 2 – Proposals for and use of claw-backAgreed

More from Liverpool Liverpool Schools Forum

All decisions
MeetingDecisionOutcome
4 Mar 2020 Minutes of Last MeetingResolved that the minutes of the meeting of the Schools Forum held on 13 January 2020 be approved as a correct record... Approved Open
4 Mar 2020 Schools Budget 202/21Resolved that – (a) the 2020-21 Schools Budgets funded from DSG be noted; and (b) the central retention element of £9... Noted Open
4 Mar 2020 SEN Inclusion Fund Early Years ConsortiaResolved that the information submitted be noted. Noted Open
4 Mar 2020 Update from Education Improvement Board (EIB)Resolved that the update be noted. Noted Open
4 Mar 2020 Update on High Needs / SEN fundingResolved that the update be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies