CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council

Work Programme Issue - Risk Management Improvement Plan

Agreed Committee 3 papers

Corporate Services Select Committee 2008/09 agreed this item on Wednesday 13 August 2008. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

Agreed that – a) the recommendation be approved; b) A further report be submitted to a future meeting in relation to equal pay claims; and c) An alternative lead officer be identified to be responsible for risk P6 once Tony Hunter leaves the authority.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Corporate Services Select Committee 2008/09, 8 pages

Reports to select committees

Liverpool City Council

Report to: Corporate Services Select Committee

Subject: Risk Management Report

Report no: F&LTRM/ 06/08

Date: 13th August 2008

Reporting officer: Susan Curran Assistant Executive Director 225 2650

Contact officer: Philip Wragg Lead Audit Manager 225 2663

1. Purpose and recommendations

To inform members about the progress made in delivering the Risk Management Policy and Strategy. This involves the continued roll-out and embedding of Risk Management at all levels throughout the council’s operations. This report also gives an update on the current position in respect of the management of the high-level risks that threaten aims at the corporate level and which are managed via the Corporate Risk Register (CRR).

RECOMMENDATIONS:- Members are asked to :

(i) Note the achievements over the last year. (ii) Note the updated Corporate Risk Register which now links to the 3 corporate key aims. (iii) Approve a further update to be provided in January 2009.

2. Relevant background information

2.1The Liverpool City Council Risk Management Policy and Strategy was approved and is personally endorsed by both the Chief Executive and the Leader of the Council.

The Risk Management Strategy commits the council to the following;

• The management of ‘business risk’ in its widest sense as understood and described by ALARM (the National Forum for Risk Management in the Public Sector).

• The promotion, encouragement and support of the practice of risk management throughout all council activities.

The Strategy also outlines a broad approach to the identification and treatment of risks as well as detailing a number of important roles and responsibilities for officers and members.

2.2CHANGING CONTEXTS:

The Strategy binds the Council into a commitment to build formal risk-based monitoring and accountability mechanisms and to embed risk management as a key element of its performance management framework.

The Strategic Risk Manager, reporting to the AED (Treasury and Risk) is responsible for the design and roll-out of actions that will deliver on the commitments in the strategy.

The scheduling of actions going forward needs to be informed by external and internal governance drivers as well as incipient changes in the council’s approach to organizing and managing its activities. An overview of current contextual changes is given in sections 2.3 to 2.7 below.

2.3CPA (& CAA) USE OF RESOURCES - KEY LINES OF ENQUIRY

It is important to take detailed account of the Key Lines of Enquiry (KLOE) for 2008 Use of Resources. The emphasis they place on Risk Management arrangements demonstrates the importance placed by the Audit Commission on the frameworks that councils have developed in this area.

From 2009, as CPA evolves into CAA, the assessment criteria are changing. The new KLOE’s are more strategic in outlook and therefore focus more on ‘outcomes’ and less on the detail of processes. This means that they are less prescriptive in terms of how risk management should ‘look’.

However, the Council should assume that its underlying approach to the management of business risk is expected to take account of the detailed elements outlined in the 2008 KLOE’s.

The Use of Resources focus from 2009 in respect of Risk requires the Council to manage its risks and maintain a sound system of internal control. The council must build on its current position to further embed risk management processes.

2.4LCC CORPORATE VISION STATEMENT

The Council has recently renewed the vision for the City. This vision is predicated upon 3 key aims:-

• Grow the City’s Economy • Empower our Residents • Develop our Communities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register Appendix 1Appendix 7 pages Download
PDF
Risk management Appendix 2Appendix 3 pages Download
PDF
Work Programme Issue: Risk Management Improvement PlanReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Work Programme Issue - Risk Management Improvement PlanThis decision
  2. Audit Committee Work Programme 2026/27Agreed
  3. Draft Audit Committee Work Programme 2026/27Agreed
  4. Audit Committee Work Programme 2025/26Agreed
  5. Audit Committee Work Programme 2025/26Agreed
  6. ESF Ways to Work Employment Support ProgrammeAgreed

More from Liverpool Corporate Services Select Committee 2008/09

All decisions
MeetingDecisionOutcome
15 Apr 2009 Minutes of the Last MeetingAgreed that – a) The minutes be approved; and b) A copy of the scheme of delegation to officers be circulated to memb... Agreed Open
15 Apr 2009 Work Programme Issue - Annual ReportAgreed that - a) The report be submitted to the Overview and Scrutiny Committee; and b) The Overview and Scrutiny com... Agreed Open
15 Apr 2009 Work Programme Issue - Future Work ProgrammeAgreed that - a) A proposed work programme be submitted for approval to the first meeting of the committee in the new... Agreed Open
15 Apr 2009 Revenues Service - Citizens' Advice Service Progress ReportAgreed that - a) The thanks of the committee be extended to the officers for their contribution in this respect; b) T... Agreed Open
15 Apr 2009 Partnership, Scrutiny, Governance and Performance of Liverpool Direct LtdAgreed that - a) Information be provided for Councillor Paul Brant in relation to – § any action which was taken in r... Agreed Open