Resolved
Agreed that Youth Capital Fund proposals, as submitted, in respect of Woolton Boys Club and Speke Catholic Youth Service be endorsed in so far as this Group is concerned.
Gateacre & Garston (South Liverpool) Youth Sub-Group agreed this item on Friday 5 September 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that Youth Capital Fund proposals, as submitted, in respect of Woolton Boys Club and Speke Catholic Youth Service be endorsed in so far as this Group is concerned.
Speke Catholic Youth Service Capital Options Analysis
Name and Address of building
Speke Catholic Youth Service
Who owns the building
The building is owned by the Catholic Archdiocese and provided on a open lease to the unit.
Provide a description of the proposed option
Speke Catholic Youth Service is on a site that includes St. Ambrose Social Club the building has a long history of providing provision for children and young people since the early 1960`s. The building has in past been used as a Boxing Club, Nursery and Play facility, since 1984 the building has been the base for inter denominational youth provision in eastern Speke.
What partnership arrangements already exist
The organisation has developed strong links with a number of organisations including Liverpool Youth Service , South Liverpool Housing, Merseyside Youth Association St. Bendicts School and St. Julies School. Members of our Management Committee also have links with local primary and secondary schools throughout the South Area.
What services/facilities will be provided as part of this proposal
The work undertaken would provide a modern accessible base for youth work projects that meets with Every Child Matters outcomes and inter agency work in order to meet the Integrated Youth Support
What are the intended objectives and outcomes?
The objectives of the unit are to support all young people between the ages of 13 and 19 years to enable them to achieve their full potential. These objectives will be met through the provision of a varied programme that provides opportunities for young people’s personal development. The outcomes will be measured by an increase in the numbers of young people accessing the facilities and taking part in the projects There is a commitment that projects will include the opportunities for young people to obtain recorded outcomes/accreditations for their achievements.
How will the proposed capital actions assist the achievement of the projects aims and objectives
We would like to be able to provide and our proposals will ensure that the general condition of the building is improved which will increase young peoples participation in the units programme. What community support exists for the capital project
The unit has the support from young people and local residents who sit as members of the Management Committee
How will young people be involved in the project The young people have already come together as a group to discuss and plan for what facilities and activities they would like to see take place at the unit. They will continue to meet and be fully included in the developing and planning of their ideas. The Management Committee are clearly committed to their view that the young people will be the main influence on how the unit is to be developed.
How many young people would access the provision It is anticipated that the number of young people accessing the building would increase to over 75 This will be achieved by the refurbishment work allowing for a wider choice of activities.
The estimated costs
Repairs to roofs and rainwater goods £4000.00
Improvements to the main entrance area and door £3,000.00
Replacement of defective kitchen fixtures and fittings, finishes & floor coverings £10,000.00
Replacement of repairs to the electrical installation to building £2,000.00
Internal decoration works £4,000.00
WC refurbishments works £10,000.00
Ventilation to kitchen and WC`s £5,000.00
Replacement internal doors and joinery £4,000.00
Installation of new suspended ceiling £5,000.00
Sub Total £ 47,000.00
Contingency £1,000.00
Total building works £48,000.00 Fees @ 13.5% £6,480.00 VAT 17.5% £9,534.00
Total £64,014.00 What is sustainability process for the project A full programme of activities will ensure the continued long term use of the project. The Management Committee also plan to offer the use of the building during the daytime to generate an income in order to maintain the project and further develop the use of the facilities for young people in the evening.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Speke Catholic Youth Service Capital Options Analyis 2Report | 3 pages | DownloadRead as text |
PDF |
Youth Capital Fund ProposalsReport | 5 pages | Download |
Follow Gateacre & Garston (South Liverpool) Youth Sub-Group at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Dec 2009 | YOF third round applicationsDecision 1026 Support 1027 Youth Service to seek to reduce the amount and verify figures with Members 1028 Support 10... | Deferred | Open |
| 4 Dec 2009 | South Liverpool Play Remodelling UpdateIt was agreed that the Sub Group re-affirm its previous decision in relation to transitional funding and seek an earl... | Agreed | Open |
| 4 Dec 2009 | Outreach work in Belle ValeAgreed that consideration of the position in relation to outreach work in Belle Vale be deferred. | Agreed | Open |
| 20 Nov 2009 | Minutes of the Last MeetingAgreed that the minutes be approved. | Agreed | Open |
| 20 Nov 2009 | Play Service Remodelling ProcessAgreed that the contents of the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.