CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 7 November 2008

Joint Merseyside Waste Development Plan (A&D/42)

Approved Executive 2 papers

Executive Board approved this item on Friday 7 November 2008. Below is the council's own wording, with the papers it was decided on.

Item76c

Resolved

Resolved that the recommendation be approved. ET/6
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Purpose of the report

The purpose of this report is to agree to undertake a consultation process on the Joint Merseyside Waste Development Plan Document Spatial Strategy and Sites Report commencing on 17th November 2008 for a period of 8 weeks.

The main content of this report can be founding Appendix 1 which follows on from this brief covering report. Appendix 1 provides a consistent Committee Report that each Merseyside district will be taking through its own approvals processes. The content of this report has been agreed by Leaders & Chief Executives at their meeting on 25th July 2008 and they have insisted that the content of the report is the same for each District’s approval process.

The key issue to note with this report is that it is purely a process report which is seeking approval to commence consultation. It is not the purpose of this report to express views on or endorse the sites or strategy set out in the consultation report.

A further report will be going to Executive Board during the consultation period where members will be able to provide their detailed comments and make decisions on the content of the Spatial Strategy and Sites report.

For information, there has been one slight change in circumstances relating to the Regional Spatial Strategy (RSS), as discussed in paragraphs 3.6-3.8 of the report, since it was drafted. The scope of Partial Review of RSS has recently been changed to exclude waste from the review. The issues associated with waste, including the development of a more complete evidence base, that was to be addressed by Partial Review of RSS will now be addressed as part of the joint work to develop a Single Regional Strategy for the North West.

Executive Member/Director recommendation: Councillor Peter Millea / John Kelly

That:

1) the City Council agrees to the commencement of an eight-week public consultation process on the Waste DPD Spatial Strategy and Sites Report in order to meet project deadlines and those set by the Secretary of State for the completion of the Regional Spatial Strategy; and

2) the Council’s agreement to the commencement of public consultation should not be taken as an endorsement of the sites or strategy set out in the consultation report and that the Council’s formal comments on these will be the subject of a further report and decision during the consultation period.

3) this issue be considered in the first instance by the Regeneration Select Committee and their views be reported to the Executive Board thereafter.

Key Decision : Yes

Forward Plan: Yes

Implementation effective from: 14 November 2008

Timescale for action:

It is intended that public consultation on the Spatial Strategy and Sites report commences on 17th November 2008.

Reason(s) for Recommendation:

To comply with the legal requirements of the Local Authorities (Functions and responsibilities) (Amendment) (No2) Regs 2005. To implement the City Council’s Local Development Scheme.

Alternative options considered

The only alternative option is to not approve the document for public consultation in which case the Waste DPD will not be able to proceed. Consultation:

Public consultation and involvement are undertaken at a number of stages during the preparation of the Waste DPD. The consultation on the Spatial Strategy and Sites report is programmed to a take place from November 17th 2008. The overall consultation processes will comply with the Councils submitted Statement of Community Involvement.

Consultation With Ward Councillors and outcome:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A&D.42 Joint Merseyside Waste Development Plan: AppendixAppendix 16 pages Download
PDF
Joint Merseyside Waste Development Plan (A&D/42)Report 4 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 16 attended
WB
Councillor Warren BradleyChair, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RG
Councillor Ron GouldMember, present
SH
Councillor Steve HurstMember, present
PK
Councillor Paula KeaveneyMember, present
GM
Councillor Gary MillarMember, present
PM
Councillor Peter MilleaMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
CA
Charlie AdanOfficer, present

All 16 on the meeting page

On this subject at Liverpool

Search all
  1. Joint Merseyside Waste Development Plan (A&D/42)This decision
  2. Merseyside and Halton Joint Waste Local Plan Review (Statutory planning document)Agreed
  3. Appointments of Members to serve on the Merseyside Joint AuthoritiesDecided
  4. Appointments of Members to serve on the Merseyside Joint AuthoritiesDecided
  5. Appointments of Members to serve on the Merseyside Joint AuthoritiesDecided
  6. Appointments of Members to serve on the Merseyside Joint AuthoritiesDecided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open