Work Programme Issue - Revenue Budget 2009/10 and Medium Term Financial Plan
AgreedCommittee1 paper
Corporate Services Select Committee 2008/09 agreed this item on Wednesday 19 November 2008. Below is the council's own wording, with the papers it was decided on.
Agreed that - a) The contents of the report be noted; b) The budget proposals and Medium Term Financial Plan be submitted to this committee in January following consideration by the Executive Board on 16 January and prior to consideration by the City Council on 28 January; and c) Information be circulated to all members of the Council in relation to the web based budget game.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Corporate Services Select Committee 2008/09, 5 pages
Reports to select committees
Liverpool City Council
Report to: All Select Committees
Subject: Revenue Budget 2009/10 and MTFP
Report no: FMS 27/08
Date:
Reporting officer: Robert Corbett, City Treasurer Tel: 225 2347 Contact officer: Robert Corbett [email protected] Ward: City Wide
1. Purpose and recommendations
To provide background to the forecast budget position for 2009/10 to assist Select Committees in considering the key issues relevant to the service responsibilities of the Select Committee.
That the report be noted and that each Select Committee give consideration to the key issues relevant to its service responsibilities.
2. Relevant background information
Financial Forecast A 3 year financial forecast is maintained based upon current level of service and having regard to estimates of future pay awards and price increases. The financial forecast also estimates future government grant support and income from council tax.
V:/Budget 0809 – Budget Process 1 Some of the key budget assumptions are as follows:
• Pay awards will average 2.5% each year.
• General price inflation affecting local authority spending will be assumed as 2% per annum but where specific price increases are known or can be forecast, then they will be provided for at the higher level, e.g. in respect of fuel and energy costs.
• Total Formula Grant (TFG) support will increase in 2009/10 by 1.75% and in 2010/11 by 1.5% in accordance with the government’s comprehensive spending review of 2007. The increase in TFG support for 2011/12 has been estimated at 1.25%. It will be noted that each of these increases is well below the anticipated rate of national inflation.
• Without any increase in council tax the collection fund income from council tax in future years will remain at current levels. Therefore, the assumption is that any increase in the council tax base will be offset by an increase in bad debts reflecting a reduction in collection performance arising from the downturn in the national and local economy.
• An increase of 1% in council tax will increase council tax income by £1.6m.
• The MTFP currently assumes a 3.9% increase in each of the 3 years 2009/10 to 2011/12.
• The financial forecasts currently provide for an increase in working balances in line with guidance from the Audit Commission. Therefore working balances are forecast as follows:
• The financial forecast for 2009/10 onwards assumed capitalisation of £2m per annum. However, if capital receipts are unable to be generated to the previously anticipated level of £6m per annum then the opportunity of funding such capitalisation will no longer be available. Therefore at this time it would be prudent to anticipate that no more than £1m of capitalisation will be able to be achieved in 2009/10 and that the forecast for future years should assume no such capitalisation.
• Core spending of approximately £4.5m per year has been financed under the former Neighbourhood Renewal Fund (NRF) and now Working Neighbourhood Fund (WNF) initiatives. However, the eligibility of such expenditure in future years cannot be relied upon. Therefore at this time, it will be prudent to anticipate that no more than £3m of eligible spending will be identified in 2009/10 and that the forecasts for future years should assume
V:/Budget 0809 – Budget Process 2 further reductions of £1.5m in each of the following two years.
Other issues The following are the longer term issues that will need to be taken into consideration for the MTFP 2009/10 to 2011/12.
• The Council is developing its cultural legacy, as a major part of its regeneration priorities, following a successful year as European Capital of Culture. That legacy is likely to require additional investment above that currently provided for within the MTFP.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Services Select Committee 2008/09 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
Work Programme Issue - Annual ReportAgreed that - a) The report be submitted to the Overview and Scrutiny Committee; and b) The Overview and Scrutiny com...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.