Resolved
Agreed that the update report on the , be noted.
Regeneration Select Committee 2008/09 agreed this item on Tuesday 16 December 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the update report on the , be noted.
2.1As Members will be aware, the Cruise Liner Terminal (CLT) was constructed at the Pier Head and was successfully opened in September 2007.
2.2The CLT was designed to provide only facilities for port of call vessels and LCC was prohibited through its funding agreements with Government Office for the North West (GONW) and North West Development Agency (NWDA) and State Aid rules, from marketing the facility as a “turnaround operation”.
2.3Prior to the opening of the terminal a number of operators approached LCC to request the use of the terminal for turnaround use. LCC sought legal advice and were informed that “they are not permitted to provide turnaround facilities for the CLT”.
The legal advice also identified that other commercial port operators could sub contract with LCC to occasionally hire the CLT for the embarkation of passengers from vessels using their own ports for turnaround. LCC were advised that in accepting these proposals that:
§ The passenger / baggage handling facility is a separate operation that is located off site / away from the cruise line facility § That no public money (ERDF or NWDA) is provided towards the cost of constructing or operating the new passenger / baggage handling facility § The cruise liner facility remains in public ownership with berthing charges levied on cruise ships at commercial rates (i.e. no benefit in kind to operator baggage handling facilities must take place off site and that the terms of the use must be on a commercial basis to avoid breaching port competition compliance rules. In addition there was to be an additional commercial gain to the private sector.)
2.4Following this advice LCC began negotiations with Peel Ports/Mersey Docks and Harbour Company (MDHC) in November 2006, as the harbour authority and the commercial port authority. The decision reached by MDHC at this time was that they did not wish to sub-contract to LCC other than at a cost unviable for LCC and Cruise Liner operators. LCC are only able to control berthing fees, with all other costs determined by MDHC as the harbour authority. The costs for ships entering the Port of Liverpool is already higher than that of other ports and the City Council is paying revenue costs of £200k per annum but could see costs rise to £400k.
2.5A counter offer was made to MDHC to offer the service at a flat fee rate or alternatively that MDHC operate the turnaround at the CLT paying a berthing charge to LCC. The proposal was declined by MDHC on 10 April 2008 on the basis of income.
3. Publicity
3.1Members will be aware that a number of statements appeared in the local press during October and November 2008 with Thomson Cruises in particular stating that they would no longer include Liverpool in their cruises due to the lack of facilities provided at Langton Dock. They also incorrectly stated that they had been given assurances that they would be able to use the LCC facility.
3.2The Executive Director for Regeneration responded with a letter to the Daily Post attached as Appendix 1 refuting these claims. He also made the same points when invited to speak on Radio Merseyside.
3.3Adverse media commentary on the state of Langton Dock as a berthing facility has fuelled demand for higher quality embarkation. The facility is owned by Peel Ports and is in the Borough of Sefton. Improvement is a matter for the owners. As to whether the city of Liverpool could and should have a high quality facility nearer the Pier Head, this matter was also addressed in the letter to the Daily Post.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cruise Liner TerminalReport | 9 pages | DownloadRead as text |
Follow Regeneration Select Committee 2008/09 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2009 | Presentation Royal Court TheatreAgreed that – (a) as the Committee wishes to see the situation resolved as soon as possible in order that ... view th... | Agreed | Open |
| 2 Apr 2009 | Notice of Motion - Local Construction JobsAgreed that the motion be noted and the issue of access to the BSI PAS 500 document be taken forward by Councillor Ti... | Agreed | Open |
| 2 Apr 2009 | Notice of Motion - Planning PolicyAgreed that the Motion be referred to the Executive Member for a response. | Agreed | Open |
| 2 Apr 2009 | Council Motion - School Crossing PatrolsAgreed that the motion be referred to the Executive Member for a response. | Agreed | Open |
| 2 Apr 2009 | Presentation - Local TransportAgreed that the presentation about the Local Transport Plan, including the 3 year transport programme, be deferred to... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.