Recycling & Waste Collection Scrutiny Panel agreed this item on Friday 19 December 2008. Below is the council's own wording, with the papers it was decided on.
Agreed that - it be recommended to the Sustainable Communities Select Committee that – “The City Council makes representations to DEFRA to give further consideration to the long term environmental and social impact of the support of incineration as detailed in the Audit Commission’s report: “Well Disposed: Responding to the Waste Challenge” with equal weight “Value for Money”. That DEFRA ensures that the Audit Commission takes a longer term view of the wider implications using in the cost / benefit analysis when decisions are taken by Waste Disposal Authorities, in particular when large scale P.F.I Schemes are being considered that will inevitably lock Authorities for periods of up to 25 years into forms of technology that might quickly be outdated and environmentally detrimental. The Audit Commission in their recent article ‘Refuse Rethink’ clearly recognises the challenges faced by Waste Disposal Authorities however fails to support any alternative solutions in the compliance with or exceed regulations standard, meet local environmental priorities and minimise future risks other than incineration”; and the Council’s Recycling and Waste Management Continuous Improvement Plan be noted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Recycling & Waste Collection Scrutiny Panel, 10 pages
RECYCLING AND WASTE MANAGEMENT CONTINUOUS IMPROVEMENT PLAN Incorporating the response to Audit Commission [Audit 2007-2008] Review of Performance (Detailed Report – August 2008)
CHIEF EXECUTIVE’S OFFICE
Performance and Evaluation 20th November 2008 (revision e)
Recycling and Waste Management Continuous Service Improvement Plan
Corporate Aim 3: Develop Own Communities
“Provide sustainable communities through best practice in environment management including, recycling, street cleansing and environmental enforcement against dereliction and environmental detractors.”
Content of the Plan
Section 1
Environmental Services Service Improvement Plan 08/09 Key planned service improvement actions EMS1 to EMS7
Section 2
Liverpool City Council’s contribution to the Audit Commission* recommendations for further development (Merseyside Waste Disposal Authority) R1 to R8
Section 3
Liverpool City Council’s response to the Audit Commission’s recommendations for areas for further development (Liverpool specific issues) AFD1 to AFD8
E:\moderngov\data\published\Intranet\C00001088\M00008789\AI00050631\WasteManagementServicesSIP20thNovember08revisione0.doc 2 Continuous Ref Actions Lead Resource Outputs and Planned Progress / Comments (evidence file reference) Improvement Officer Impact Outcomes
Corporate Aim 3 Develop LCC Corporate Plan 2008/09 – 2010/11 AED Lead Contribution to Corporate Aim 3: Develop Our Communities and Key Actions Our Communities: Jan Rowley 2008/09 Existing Planned Service Improvements: “Provide sustainable Key actions as 2008/09 communities through EMS1 • Establish and deliver the neighbourhood Andrew Improve Environmental On target best practice in enforcement programme (March 2009) McCartan Management and Reduction in • Enforcement review currently complete, recommendations for a new environment Anti-Social Behaviour unified enforcement team accepted, consultation with Staff and TU in management including, progress. Enforcement to be directed by AED & become an integral part recycling, street of environmental management. cleansing and environmental EMS2 • Deliver fortnightly recycling to remaining 60 Andrew Funded from 100% Recycling Collection Completed 31 August 08 enforcement against schools and 180 apartment blocks to McCartan efficiencies Service across the City dereliction and ensure 100% service coverage by year end resulting from (CAP Aim 3 ) environmental (31 August 2008) procurement detractors.” EMS3 • Deliver the procurement of the new waste Keith Reduction in cost Enhanced Recycling and Waste Contract awarded 20th June 2008. Mobilisation Plans drafted for new contract Existing Planned Service collection contract for refuse/recycling to Cadman of Waste Collection Service to deliver: and transfer of staff. Improvement 08/09 support the delivery of joint municipal waste Management – NI 192 - % of household waste th management strategy and statutory efficiencies from sent for recycling (08/09 Tgt New contract commenced as planned on 8 November 08. TUPE transfer of document (7 November 2008) procurement 25%) 300 staff, new contractor EL establish new integrated Waste Collection Service £1.8m (LAA & CAP: Aim 3) from new depot facility (refuse collection, recycling collections, trade waste RHE0024 – New service for collections) waste collection (08/09 target – Nov 2008)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Recycling & Waste Collection Scrutiny Panel at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.