Risk Management

Agreed Committee 2 papers

Corporate Services Select Committee 2008/09 agreed this item on Wednesday 7 January 2009. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

Agreed that the contents of the report be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Corporate Services Select Committee 2008/09, 5 pages

APPENDIX 1 RISK MANAGEMENT PROJECT PLAN AT 2-1-09 Key:- IN PLAN UNDERWAY COMPLETE

31/12/2008

31/03/2009

30/06/2009

30/09/2009

Ongoing REFERENCE TASK

Ensure that a senior officer and member jointly champion and take responsibility for 1 embedding risk management throughout the council. 2 Re-work and update Corporate Risk Register prior to first meeting of CRMG (see 6). 3 Identification of AED level RM champions.

4 Identification of process level RM champions (managers) within Business Units.

5 Establish and hold first meeting of RM Project Control Group

6 Establish and hold first meeting of Corporate Risk Management Group (CRMG)

Link in with new corporate Project Management Methodology. Ensure there is a RM 7 ‘technical adviser’. Identify and link into established benchmarking programmes with peer authorities and 8 partners. 9 Create Risk Appetite statement for consideration by CRMG.

10 Pick up and move forward with the Partnership Scrutiny process. APPENDIX 1 RISK MANAGEMENT PROJECT PLAN AT 2-1-09 Key:- IN PLAN UNDERWAY COMPLETE

31/12/2008

31/03/2009

30/06/2009

30/09/2009

Ongoing REFERENCE TASK

Discussion/planning forums to understand what is in place, what has worked, what 11 hasn’t worked – and what the customer (service management) wants.

Stock-take of the training delivered thus far (including feedback sessions to analyse 12 effectiveness).

13 Re-consideration of training programme in light of stock-take / feedback.

Re-consideration and continual development of training to take account of changing RM 14 landscape and approach. Ensure training/education covers linkages with broader council improvement programme and external drivers (such as CAA). Detailed meetings with key individuals including Head of Scrutiny and Best Value and 15 Head of Audit to ensure RM approach is properly joined up and linked in with other council-wide and risk-based initiatives 16 Ongoing reworking of Corporate Risk Register to reflect CRMG decisions.

Consider purchase of dedicated Risk Reporting software. Liaise with Head of Audit to 17 ensure that a single solution that benefits all is procured. APPENDIX 1 RISK MANAGEMENT PROJECT PLAN AT 2-1-09 Key:- IN PLAN UNDERWAY COMPLETE

31/12/2008

31/03/2009

30/06/2009

30/09/2009

Ongoing REFERENCE TASK

Audit of Service Plans (risk register elements) to ensure that there is consistency of approach and terminology. Provision of facilitated sessions (risk workshops or one-to- 18 ones) with service heads (where necessary) to help them in identifying and measuring the risks that matter to the council.

19 Re-work and disseminate the Risk Management Policy and Strategy.

Re-visit and re-publicise the roles and responsibilities for managing risk that form part 20 of the RM policy/Strategy.

Refinement of training framework pitched at appropriate levels :- Development of a two- 21 stage programme aimed at:- raising awareness and understand - training re Use of RM Processes when finalised. APPENDIX 1 RISK MANAGEMENT PROJECT PLAN AT 2-1-09 Key:- IN PLAN UNDERWAY COMPLETE

31/12/2008

31/03/2009

30/06/2009

30/09/2009

Ongoing REFERENCE TASK

22 Publish the Risk Management Delivery Plan.

23 Refresh, rework and reinvigorate Risk Management Intranet pages.

Develop and promote links from officers to Strategic Risk Manager (and team) to 24 ensure that a clear and accessible support channel is in place.

Induction training for all New managers in the principles of Risk Management. Work 25 with HR to ensure that Risk Management awareness is built into New Starter packs. Ensure new competencies adequately reflect RM.

Encourage continued and improved Member satisfaction with the principles of risk and 26 their understanding of RM principles via further dedicated sessions

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Plan at 2-1-09Report 5 pages DownloadRead as text
PDF
Risk ManagementReport 5 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Risk ManagementThis decision
  2. Risk Management UpdateAgreed
  3. Risk Management UpdateAgreed
  4. Risk Management UpdateAgreed
  5. Adoption of Liverpool's Local Flood Risk Management Strategy (HCS/11)Approved
  6. Risk Management StrategyApproved

More from Liverpool Corporate Services Select Committee 2008/09

All decisions
MeetingDecisionOutcome
15 Apr 2009 Minutes of the Last MeetingAgreed that – a) The minutes be approved; and b) A copy of the scheme of delegation to officers be circulated to memb... Agreed Open
15 Apr 2009 Work Programme Issue - Annual ReportAgreed that - a) The report be submitted to the Overview and Scrutiny Committee; and b) The Overview and Scrutiny com... Agreed Open
15 Apr 2009 Work Programme Issue - Future Work ProgrammeAgreed that - a) A proposed work programme be submitted for approval to the first meeting of the committee in the new... Agreed Open
15 Apr 2009 Revenues Service - Citizens' Advice Service Progress ReportAgreed that - a) The thanks of the committee be extended to the officers for their contribution in this respect; b) T... Agreed Open
15 Apr 2009 Partnership, Scrutiny, Governance and Performance of Liverpool Direct LtdAgreed that - a) Information be provided for Councillor Paul Brant in relation to – § any action which was taken in r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies