Agreed that - a) The contents of the report be noted; b) Given that Liverpool’s results from the customer survey questionnaires are higher than any other core cities, comparative information be provided for the other core cities; c) The Head of Internal Audit be requested to provide a briefing for the ward councillors once the due diligence review of the assets of the Kensington New Deal for Communities has been completed; and d) In future an explanation be included in the report when planned work is removed from the plan.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Audit and Accounts Committee 2007/2013, 14 pages
Liverpool City Council
Report to: Audit and Accounts Committee
Subject: Internal Audit Progress Report to December 2008 Report no: Audit / 22 / 2009
Date: 11 February 2009
Reporting officer: Karen Lowe, Head of Internal Audit
Contact officer: K Lowe – 225 2651
Ward: All
1. Purpose and recommendations
Purpose: To present to members an update on Internal Audit work in the third quarter of 2008/09, a summary of the year-to-date audit opinions, the current position against the annual audit plan and a review of the Internal Audit service against its performance indicators. Recommendation: That, in accordance with the terms of reference for the Audit & Accounts Committee, members comment on and raise any issues they consider significant in respect of the Internal Audit progress report for the third quarter of 2008/09.
2. Relevant background information The terms of reference for the Audit & Accounts Committee include: “consider…the control environment…, seek assurances that action is being taken on risk-related issues identified by auditors .., monitor [Internal Audit’s] performance”. The aim of this progress report is to help members fulfil the above role by providing a broad summary of Internal Audit activities for the quarter up to 30 September 2008 and its performance for the first half of the year.
3. Key issues
In the last quarter a further 15 pieces of planned audit work have been completed but the year to date overall position on the level of control weaknesses remains unchanged in that 73% of the completed planned work identified control weaknesses and non-compliance with procedures and basic controls that were placing the service objectives at risk and in some cases meant that the relevant risks were not being managed at all.
As a result Audit are planning to role out a programme of internal control training early in the new financial year and will be offering guidance to heads of business units in completing those sections of their business plans that link to controls. The ongoing work between Internal Audit and the Corporate Risk Manager in sharing and acting on the results of risk-based audits, etc will assist in the overall improvement of internal controls and risk management.
As regards the Internal Audit service’s own performance, the audit plan is still on schedule to be completed by the year end but recognise that there are often delays in getting draft reports out to customers. Despite this, feedback from customers on our overall performance remains positive, exceeds target and the results of other core cities.
4. Equalities Implications /Equality Impact Assessment There are no equalities implications arising from this report
5. Conclusions Internal controls need to be improved across the council as a matter of priority. A failure to do so is likely to impact on the 2008/9 Use of Resources assessment.
The Internal Audit service need to issue draft audit reports far quicker than current practise.
6. Key to any abbreviations used As indicated in the Internal Audit Progress Report attached. 7. Documents attached Internal Audit Progress Report for the quarter ended 31 December 2008.
INTERNAL AUDIT PROGRESS REPORT as at 31 December 2008
1. AUDIT WORK IN QUARTER 3 The main audits and responsive work started and / or completed in Quarter 3 were as follows:
1.1CROSS-CUTTING
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit and Accounts Committee 2007/2013 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.