Work Programme Issue - Strategic Innovation and Improvement Plan - Progress Report

Agreed Committee 4 papers

Corporate Services Select Committee 2008/09 agreed this item on Wednesday 25 February 2009. Below is the council's own wording, with the papers it was decided on.

Item83

Resolved

Agreed that – a) The contents of the report be noted; and b) Clarification be provided in relation to the roll out of the pilot for members personal web sites, the provision of a members’ bulletin and arrangements to support members in their community leadership role.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Corporate Services Select Committee 2008/09, 8 pages

Strategic innovation and improvement plan: area for improvement 1 - future ambitions and delivery Date 05/02/09 The council is developing its new sustainable communities strategy. As part of this work with partners it is updating the vision for Liverpool, and establishing some specific targets of what success will look like in the long term. This will inform the updated local area agreement priorities and targets and the Council’s refreshed corporate priorities – which need to be clearer and more focused. The Council has recognised the need to further develop the infrastructure to support its wide and challenging improvement agenda. To underpin this, the Council needs to develop a clear set of strategies and supporting action plans for delivery such as in asset management and procurement. What success looks like: the LAA and LCC corporate plan targets are met, and we can evidence we are closing the gap with our peers; residents' satisfaction is above the average of our peers

Progress to date on planned actions and key milestones and Traffic light Planned actions and key milestones to deliver strategic Date to be Lead ED/ impact/outcome achieved against Strategic outcomes outcome completed officer (RAG for each action - R = action behind schedule, A = action on track, strategic but not complete, G = action complete) outcome

The city council engages with stakeholders City council agrees its revised long-term vision - with rationalised 04/08/08 Colin Hilton Vision, aims and priorities agreed jointly by EMT/EMB and formally G and communities to develop and agree a long- set of aims and priorities approval by council 6th March 2008. Paper produced for Leader term vision, key themes and medium term immediately following May elections, which confirmed approach and key priorities behind which it aligns its strategic, issues. (G) financial and business planning. The LAA has been approved by Government and the sustainable communities strategy (SCS) has established the vision for 2024. There are a series of bilateral discussions with key stakeholders to look at how the vision can inspire the leadership of the city, can capture the distinctive nature of Liverpool and can best articulate the vision. ( G)

The changes to the council's constitution to give clarity of political alignment were completed in May 2008. The restructuring of the senior management of the council completed to the deadline by Council approval on 15 October 2008. N.B. Structured business and financial planning and business unit programme aligned to priorities reported under strand 2. (G)

The political leadership of the city council has defined a finer grain of detail for its priorities within the framework of the SCS and the council’s overall aims and these were published on 1st July 2008. (G)

Consultation on the SCS has been completed. The document has been completed and signed-off by the Liverpool First board. (G)

The running order of the priorities and outcomes of both the council's corporate plan and the community strategy have been amended to better evidence the clear alignment in objectives between the two key documents (G)

Page 1 Progress to date on planned actions and key milestones and Traffic light Planned actions and key milestones to deliver strategic Date to be Lead ED/ impact/outcome achieved against Strategic outcomes outcome completed officer (RAG for each action - R = action behind schedule, A = action on track, strategic but not complete, G = action complete) outcome

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1: future ambition delivery: master 5-Feb-09Report 8 pages DownloadRead as text
PDF
2: Finance-master 5-Feb-09Report 6 pages Download
PDF
3: organisational culture governance: master 5-Feb-09Report 7 pages Download
PDF
Work Programme Issue: Strategic Innovation and Improvement Plan: Progress ReportReport 2 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Work Programme Issue - Strategic Innovation and Improvement Plan - Progress ReportThis decision
  2. Audit Committee Work Programme 2026/27Agreed
  3. Draft Audit Committee Work Programme 2026/27Agreed
  4. Audit Committee Work Programme 2025/26Agreed
  5. Audit Committee Work Programme 2025/26Agreed
  6. ESF Ways to Work Employment Support ProgrammeAgreed

More from Liverpool Corporate Services Select Committee 2008/09

All decisions
MeetingDecisionOutcome
15 Apr 2009 Minutes of the Last MeetingAgreed that – a) The minutes be approved; and b) A copy of the scheme of delegation to officers be circulated to memb... Agreed Open
15 Apr 2009 Work Programme Issue - Annual ReportAgreed that - a) The report be submitted to the Overview and Scrutiny Committee; and b) The Overview and Scrutiny com... Agreed Open
15 Apr 2009 Work Programme Issue - Future Work ProgrammeAgreed that - a) A proposed work programme be submitted for approval to the first meeting of the committee in the new... Agreed Open
15 Apr 2009 Revenues Service - Citizens' Advice Service Progress ReportAgreed that - a) The thanks of the committee be extended to the officers for their contribution in this respect; b) T... Agreed Open